Complete project overview

RERA Telangana · Registration filing
Units
277 units
Unit mix
277 × 2BHK
Saleable area
54–80 sq mper unit, as filed
Floors
10
Land area
51,536 sq m
Built-up area
28,369 sq m
Road widening
1,619 sq mland set aside for road widening

Timeline

RERA approvedSep 2018
Proposed completionAug 2024
TodayJul 2026
Construction progress

42% overall, as filed

Podiums0%
Stilt floor0%
Flat fit-out0%
External finishes0%
OC-readiness0%
Stairs & lifts20%
Excavation100%
Basement & plinth100%
Superstructure100%
Internal finishes100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

112 of 277 available
BuildingFloorTypeArea sq mAvailable
SITARA A212BHK540 of 2
SITARA A212BHK590 of 3
SITARA A212BHK693 of 4
SITARA A212BHK751 of 4
SITARA A212BHK754 of 8
SITARA A212BHK762 of 4
SITARA A222BHK540 of 4
SITARA A222BHK590 of 4
SITARA A222BHK691 of 4
SITARA A222BHK752 of 4
SITARA A222BHK752 of 8
SITARA A222BHK760 of 4
SITARA A232BHKmortgaged540 of 4
SITARA A232BHKmortgaged590 of 4
SITARA A232BHKmortgaged691 of 4
SITARA A232BHKmortgaged792 of 12
SITARA A232BHKmortgaged800 of 4
SITARA A242BHK540 of 4
SITARA A242BHK590 of 4
SITARA A242BHK692 of 4
SITARA A242BHK791 of 12
SITARA A242BHK800 of 4
SITARA A252BHK541 of 4
SITARA A252BHK590 of 4
SITARA A252BHK692 of 4
SITARA A252BHK792 of 12
SITARA A252BHK800 of 4
SITARA A262BHK540 of 4
SITARA A262BHK590 of 4
SITARA A262BHK693 of 4
SITARA A262BHK793 of 12
SITARA A262BHK800 of 4
SITARA A272BHK544 of 4
SITARA A272BHK594 of 4
SITARA A272BHK694 of 4
SITARA A272BHK7912 of 12
SITARA A272BHK800 of 4
SITARA A282BHK544 of 4
SITARA A282BHK594 of 4
SITARA A282BHK694 of 4
SITARA A282BHK7912 of 12
SITARA A282BHK800 of 4
SITARA A292BHK694 of 4
SITARA A292BHK542 of 4
SITARA A292BHK592 of 4
SITARA A292BHK795 of 12
SITARA A292BHK800 of 4
SITARA A2102BHK694 of 4
SITARA A2102BHK543 of 4
SITARA A2102BHK593 of 4
SITARA A2102BHK797 of 12
SITARA A2102BHK802 of 4

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

JANAPRIYA PROJECTS

PartnershipPromoter type
Hyderabad, TelanganaBased in
8Projects
1City
2017–2024Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,908 homeson the public record across 8 projects
2,01,438 sq mbuilt-up filed
4,12,288 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
YELLAREDDYGUDA
Mandal
Keesara
District
Medchal-Malkajgiri
Pincode
500062
North boundary
OPEN SPACE BETWEEN AMENITIES BLOCK
East boundary
OPEN SPACE BETWEEN NAIGHBOURS LAND
South boundary
OPEN SPACE BETWEEN BLOCK A4
West boundary
OPEN SPACE BETWEEN BLOCK A1
What’s nearby
SchoolsNearest school 1.4km away
HealthcareHospital 472m away · Clinic within 2km
LifestyleNo parks within 2km · Gym or sports centre 1.4km away
ShoppingSupermarket 601m away · Mall 1.5km away
Getting around
Primary road 1.7 km · Kushaiguda RoadRailway line 3.3 kmRailway station 3.3km away (Neredmet)Limited bus connectivity nearby
Water & environment
Water body 1.2 km · Kapra lake
distances only — not a flood assessment
Declared external development
Sewerage (Chamber,…100%
Roads0%
Water supply0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit no. 53506/HO/EZ/Cir-1/20Survey no. 663 P, 667, 668 AND 671 P

The promised possession date (20 Aug 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 53506/HO/EZ/Cir-1/20 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.