Timeline

Project startedJul 2022
RERA registeredMar 2023
Proposed completionDec 2027
TodayJul 2026
Construction progress

99% overall, as filed

Overall % complete as filed with GujRERA, taken as the slowest of the project's blocks — a snapshot, not a live tracker. Where a BU permission is on record (section 04), that is the firmer completion signal.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

224 units across 1 batch
TypeArea sq mCount
Flat95224

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

GujRERA · Promoter registration

SHREEJI ENTERPRISE

PARTNERSHIP FIRMPromoter type
Surat, GujaratBased in
25Projects
9Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,355 homeson the public record across 25 projects
60,928 sq mbuilt-up filed
68,120 sq mland declared
₹379.58 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Vadodara Municipal CorporationMunicipal / Corporation5 of 22 projects
Others3 of 22 projects
Rajkot Municipal CorporationMunicipal / Corporation3 of 22 projects
Rajkot Urban Development AuthorityUrban Development Authority3 of 22 projects
Surat Urban Development AuthorityUrban Development Authoritythis project3 of 22 projects
Ahmedabad Municipal CorporationMunicipal / Corporation1 of 22 projects
Anand VallabhVidhyanagar Karmsad Urban Development AuthorityUrban Development Authority1 of 22 projects
Gandhinagar Urban Development AuthorityUrban Development Authority1 of 22 projects
Surat Municipal CorporationMunicipal / Corporation1 of 22 projects
Vadodara Urban Development AuthorityUrban Development Authority1 of 22 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

GujRERA · Registration filing
Taluka
Surat City
District
Surat
Address
T.P.S. NO: 43 (BHIMRAD), BLOCK NO.103, F.P. NO : 14, O.P. NO : 43, MOJE : BHIMRAD, TAL : MAJURA, DIST : SURAT
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 59m away · 2 clinics within 1km · Doctor's clinic within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km · Mall 1.6km away
Getting around
Expressway 1.6 kmPrimary road 1.0 kmMetro station 123m away (Surat Women ITI)Limited bus connectivity nearby
Water & environment
River 462 mWater body 1.4 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹106.61 Cr declared to build 224 flats. What that works out to:

₹53.51 Lakhdeclared unit pricerange on the filing — not a live asking price
₹47.59 Lakhdeclared cost per flatall-in — land + construction
₹4,637/sq ftof carpet area₹49,909/sq m
13%of the cost is land₹1,882/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

GujRERA · Approved building plan

Surat Urban Development Authority

Urban Development Authority
Building Permitapproved 14 Mar 2023 · 3 yrs ago
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Surat Urban Development Authority

Urban Development Authority

Has approved 895 RERA projectsabout 1 in 19 in Gujarat.

a mixed market65% apartments · 35% plotted layouts.

Builders
734
On record
1,12,087 flats · 25,390 plots
Reach
14 talukas
Since
2008

More layout-heavy than Gujarat overall — 35% plots here vs 6% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Complaints — GujRERA does not publish a complaints register. This read cannot speak to them either way.