01
Complete project overview
RERA Telangana · Registration filing- Units
- 128 units
- Unit mix
- 76 × 2BHK, 52 × 3BHK
- Saleable area
- 97–170 sq mper unit, as filed
- Floors
- 11
- Land area
- 4,250 sq m
- Built-up area
- 16,006 sq m
Timeline
Proposed completionSep 2029
Construction progress0% overall, as filed
Excavation0%
Basement & plinth0%
Podiums0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block. BuildingFloorTypeArea sq mAvailable
SKY PLAZA13BHKmortgaged1481 of 1
SKY PLAZA12BHKmortgaged1252 of 2
SKY PLAZA12BHKmortgaged1044 of 4
SKY PLAZA13BHKmortgaged1461 of 1
SKY PLAZA23BHK1631 of 1
SKY PLAZA23BHK1701 of 1
SKY PLAZA23BHKmortgaged1432 of 2
SKY PLAZA22BHKmortgaged973 of 3
SKY PLAZA23BHKmortgaged1461 of 1
SKY PLAZA22BHKmortgaged1214 of 4
SKY PLAZA33BHK1631 of 1
SKY PLAZA33BHK1432 of 2
SKY PLAZA32BHK973 of 3
SKY PLAZA33BHK1461 of 1
SKY PLAZA32BHK1214 of 4
SKY PLAZA33BHK1701 of 1
SKY PLAZA43BHK1631 of 1
SKY PLAZA43BHK1432 of 2
SKY PLAZA42BHK973 of 3
SKY PLAZA43BHK1461 of 1
SKY PLAZA42BHK1214 of 4
SKY PLAZA43BHK1701 of 1
SKY PLAZA53BHK1631 of 1
SKY PLAZA53BHK1432 of 2
SKY PLAZA52BHK973 of 3
SKY PLAZA53BHK1461 of 1
SKY PLAZA52BHK1214 of 4
SKY PLAZA53BHK1701 of 1
SKY PLAZA63BHK1631 of 1
SKY PLAZA63BHK1432 of 2
SKY PLAZA62BHK973 of 3
SKY PLAZA63BHK1461 of 1
SKY PLAZA62BHK1214 of 4
SKY PLAZA63BHK1701 of 1
SKY PLAZA73BHK1631 of 1
SKY PLAZA73BHK1432 of 2
SKY PLAZA72BHK973 of 3
SKY PLAZA73BHK1461 of 1
SKY PLAZA72BHK1214 of 4
SKY PLAZA73BHK1701 of 1
SKY PLAZA83BHK1631 of 1
SKY PLAZA83BHK1432 of 2
SKY PLAZA82BHK973 of 3
SKY PLAZA83BHK1461 of 1
SKY PLAZA82BHK1214 of 4
SKY PLAZA83BHK1701 of 1
SKY PLAZA93BHK1631 of 1
SKY PLAZA93BHK1432 of 2
SKY PLAZA92BHK973 of 3
SKY PLAZA93BHK1461 of 1
SKY PLAZA92BHK1214 of 4
SKY PLAZA93BHK1701 of 1
SKY PLAZA103BHK1631 of 1
SKY PLAZA103BHK1432 of 2
SKY PLAZA102BHK973 of 3
SKY PLAZA103BHK1461 of 1
SKY PLAZA102BHK1214 of 4
SKY PLAZA103BHK1701 of 1
SKY PLAZA113BHK1631 of 1
SKY PLAZA113BHK1432 of 2
SKY PLAZA112BHK973 of 3
SKY PLAZA113BHK1461 of 1
SKY PLAZA112BHK1214 of 4
SKY PLAZA113BHK1701 of 1
Complete project overview — done
02
Builder’s track record
RERA Telangana · Promoter registrationSUNRISE BUILDERS AND DEVELOPERS
PartnershipPromoter type
Medchal-Malkajgiri, TelanganaBased in
5Projects
4Cities
2019–presentActive
Timelineevery project, start → promised completion
20192020202120222023202420252026202720282029today
Builder DNAthe whole portfolio, summed
288 homeson the public record across 5 projects
37,831 sq mbuilt-up filed
12,136 sq mland declared
Planning authoritiesthis builder's portfolio, by approving body
Directorate of Town & Country Planning (DTCP)Town & Country Planning (DTCP)1 of 4 projects
Greater Hyderabad Municipal Corporation (GHMC)Municipal / Corporationthis project1 of 4 projects
Hyderabad Metropolitan Development Authority (HMDA)Urban Development Authority1 of 4 projects
Kalyan Dombivli Municipal CorporationMunicipal Corporation1 of 4 projects
Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Builder's track record — done
03
Location
RERA Telangana · Registration filing- Locality
- HAYATHNAGAR
- Village
- Anmagal
- Mandal
- Hayathnagar
- District
- Ranga Reddy
- Pincode
- 500070
What’s nearbySchools2 schools within 500m · 5 educational institutions within 1km · College or university 1.1km away
HealthcareHospital 359m away · 5 clinics within 1km · Pharmacy within 500m
LifestylePark 869m away · Gym or sports centre 235m away · 12+ restaurants and cafes within 1km
ShoppingSupermarket 172m away · Mall 1.7km away · Convenience store within 1km
Getting aroundExpressway 860 m · Vijaywada HighwayPrimary road 1.8 km · Hyderabad - Nagarjuna Sagar RoadMetro station 3.7km away (L. B. Nagar Metro Station)Bus stop within 500m
Water & environmentWater body 1.7 km · Kappala Cheruvu
distances only — not a flood assessment Declared external developmentRoads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot. Location — done
04
Planning authority
RERA Telangana · Approved building planGreater Hyderabad Municipal Corporation (GHMC)
Municipal / CorporationBuilding Permit
Survey no. 141/A/A,141/A/AA,141/A/1/2
The occupancy certificate — the proof that isn’t hereA sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.
The approving body, at scale
GHMC
Municipal Corporation · Hyderabad city coreHas approved 3,102 RERA projects — about 1 in 4 in Telangana.
an apartments market — 99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.
- Builders
- 1,994
- On record
- 2,20,211 flats · 3,387 plots
- Reach
- 65 mandals
- Since
- 2016
More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.
Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.
Planning authority — done
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.
- Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.