HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
15 units
Unit mix
14 × 2BHK, 1 × 2bhl
Saleable area
82–96 sq mper unit, as filed
Floors
5
Land area
614 sq m
Built-up area
1,371 sq m

Timeline

RERA approvedApr 2018
Proposed completionDec 2020
TodayJul 2026
Construction progress

51% overall, as filed

Basement & plinth0%
Podiums0%
External finishes0%
OC-readiness10%
Internal finishes40%
Stairs & lifts70%
Flat fit-out90%
Excavation100%
Stilt floor100%
Superstructure100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

14 of 15 available
BuildingFloorTypeArea sq mAvailable
skylar grand orchid12BHK821 of 1
skylar grand orchid12BHK962 of 2
skylar grand orchid22BHKmortgaged961 of 1
skylar grand orchid22BHKmortgaged821 of 1
skylar grand orchid22BHK821 of 1
skylar grand orchid32BHK821 of 1
skylar grand orchid32BHK962 of 2
skylar grand orchid42BHK820 of 1
skylar grand orchid42BHK962 of 2
skylar grand orchid52bhl961 of 1
skylar grand orchid52BHK961 of 1
skylar grand orchid52BHK821 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

SKYLAR BUILDERS

PartnershipPromoter type
Hyderabad, TelanganaBased in
4Projects
1City
2018–2024Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
60 homeson the public record across 4 projects
6,113 sq mbuilt-up filed
2,690 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
gundlapochampally
Mandal
Medchal
District
Medchal-Malkajgiri
Pincode
500043
North boundary
neighbour land
East boundary
40 feet road
South boundary
plot no 81
West boundary
plot no 63 64 65
What’s nearby
SchoolsNo schools within 2km · College or university 1.0km away
HealthcareHospital 338m away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km · Mall 1.4km away
Getting around
Expressway 909 mPrimary road 326 m · Hyderabad-Narsapur RoadNo metro or railway within 5kmBus stop within 500m
Water & environment
Water body 392 m
distances only — not a flood assessment
Declared external development
Rainwater50%
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Hyderabad Metropolitan Development Authority (HMDA)

Urban Development Authority
Building Permit no. 007171/MED/R1/U6/HMDSurvey no. 523/1 and 2, 523/9, 524, 388/1 and 388/2

The promised possession date (31 Dec 2020) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 007171/MED/R1/U6/HMD on the approving authority’s portal to confirm the sanction.

The approving body, at scale

HMDA

Urban Development Authority · Hyderabad metropolitan periphery

Has approved 3,643 RERA projectsabout 1 in 3 in Telangana.

an apartments market72% apartments · 28% plotted layouts. Apartments like yours are this body's core business.

Builders
2,462
On record
3,98,695 flats · 1,96,015 plots
Reach
71 mandals
Since
2016

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.