HORIZONMarkets
01

Complete project overview

RAJ-RERA · Registration filing
Land area
750 sq m
Description
Due to some mistake, Land and development cost were left out to be filled under Project Cost category. Resulting to which, no values for land and development cost are further taken. So, following values should be considered for the Project Cost:- Land Cost as per Rule 5(1)- INR 1,01,50,000/- Development Cost as per Rule 5(2)- INR 4,00,00,000/- Total Cost- INR 5,01,50,000/-

Timeline

Construction startFeb 2018
RERA registeredMay 2018
Proposed completionJan 2025
TodayJul 2026
02

Builder’s track record

RAJ-RERA · Promoter registration

SOMYA BUILDCON LLP

OrganisationPromoter type
Jaipur, RajasthanBased in
6Projects
1City
2018–2025Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
138 homeson the public record across 6 projects
24,776 sq mbuilt-up filed
7,803 sq mland declared
₹49.34 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RAJ-RERA · Registration filing
Address
C-153, MAHAL YOJANA, JAGATPURA, VILLAGE MAHAL,, JAIPUR, Sanganer, Jaipur, 302017
Village
JAIPUR
Taluka
Sanganer
District
Jaipur
Pincode
302017
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 914m away · Clinic within 2km
LifestyleNo parks within 2km · Gym or sports centre 1.9km away
ShoppingNo supermarket within 2km
Getting around
Expressway 3.2 kmRailway line 3.1 kmNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 742 mCanal 1.0 km
distances only — not a flood assessment
04

Planning authority

RAJ-RERA · Approved building plan

Jaipur Development Authority

Development Authority
Building Permitapproved 21 May 2018 · 8 yrs ago

The promised possession date (10 Jan 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Jaipur Development Authority

Development authority

Has approved 644 RERA projectsabout 1 in 3 in Rajasthan, more than any other body in the state.

a mixed market52% apartments · 48% plotted layouts.

Builders
528
On record
15,937 flats · 30,970 plots
Reach
2 districts
Since
2017

More apartment-heavy than Rajasthan overall — 52% apartments here vs 34% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.