HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
140 units
Unit mix
105 × 2BHK, 32 × 3BHK, 3 × Amenities
Saleable area
107–163 sq mper unit, as filed
Floors
5
Land area
7,283 sq m
Built-up area
15,743 sq m
Road widening
535 sq mland set aside for road widening

Timeline

RERA approvedJan 2020
Proposed completionJan 2026
TodayJul 2026
Construction progress

24% overall, as filed

Basement & plinth0%
Podiums0%
Internal finishes0%
Flat fit-out0%
External finishes0%
OC-readiness0%
Superstructure20%
Stairs & lifts20%
Excavation100%
Stilt floor100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

140 of 140 available
BuildingFloorTypeArea sq mAvailable
SR FORTUNE CITY13BHKmortgaged1461 of 1
SR FORTUNE CITY13BHKmortgaged1392 of 2
SR FORTUNE CITY12BHKmortgaged11110 of 10
SR FORTUNE CITY13BHK1461 of 1
SR FORTUNE CITY12BHK1076 of 6
SR FORTUNE CITY12BHKmortgaged1074 of 4
SR FORTUNE CITY12BHK1161 of 1
SR FORTUNE CITY13BHK1531 of 1
SR FORTUNE CITY13BHKmortgaged1561 of 1
SR FORTUNE CITY1Amenities1631 of 1
SR FORTUNE CITY23BHK1462 of 2
SR FORTUNE CITY23BHK1392 of 2
SR FORTUNE CITY22BHK11110 of 10
SR FORTUNE CITY22BHK10710 of 10
SR FORTUNE CITY22BHK1161 of 1
SR FORTUNE CITY23BHK1531 of 1
SR FORTUNE CITY23BHK1561 of 1
SR FORTUNE CITY2Amenities1631 of 1
SR FORTUNE CITY33BHK1462 of 2
SR FORTUNE CITY33BHK1392 of 2
SR FORTUNE CITY32BHK11110 of 10
SR FORTUNE CITY32BHK10710 of 10
SR FORTUNE CITY32BHK1161 of 1
SR FORTUNE CITY33BHK1531 of 1
SR FORTUNE CITY33BHK1561 of 1
SR FORTUNE CITY3Amenities1631 of 1
SR FORTUNE CITY43BHK1462 of 2
SR FORTUNE CITY43BHK1392 of 2
SR FORTUNE CITY42BHK11110 of 10
SR FORTUNE CITY42BHK1079 of 9
SR FORTUNE CITY42BHK1071 of 1
SR FORTUNE CITY42BHK1161 of 1
SR FORTUNE CITY43BHK1531 of 1
SR FORTUNE CITY43BHK1561 of 1
SR FORTUNE CITY43BHK1631 of 1
SR FORTUNE CITY53BHK1462 of 2
SR FORTUNE CITY53BHK1392 of 2
SR FORTUNE CITY52BHK11110 of 10
SR FORTUNE CITY52BHK10710 of 10
SR FORTUNE CITY52BHK1161 of 1
SR FORTUNE CITY53BHK1531 of 1
SR FORTUNE CITY53BHK1561 of 1
SR FORTUNE CITY53BHK1631 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

SRI SAI CONSTRUCTIONS & ABHIRAM CONSTRUCTIONS

OthersPromoter type
Ranga Reddy, TelanganaBased in
1Projects
1City
2020–2026Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
MAKTHA MAHABOOBPET
Village
Makutha
Mandal
Serilingampally
District
Ranga Reddy
Pincode
500049
North boundary
SURVEY NOs 34 AND 44 P
East boundary
NAGARJUNA ENCLAVE
South boundary
SURVEY NO 44 P
West boundary
SURVEY NO 30
What’s nearby
Schools2 schools within 1km · 3 educational institutions within 1km · College or university 1.3km away
HealthcareHospital 834m away · 1 clinic within 1km · Pharmacy within 1km
LifestylePark 918m away · Gym or sports centre 966m away · 41+ restaurants and cafes within 1km
ShoppingSupermarket 650m away · Mall 1.1km away · Bank 211m away
Getting around
Primary road 189 mRailway line 3.0 kmMetro station 417m away (Raidurg)2 bus stops within 500m
Water & environment
Water body 301 m
distances only — not a flood assessment
Declared external development
Water supply80%
Community Building…20%
Roads0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit no. 1/C21/00382/2020Survey no. 32 & 33

The promised possession date (9 Jan 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 1/C21/00382/2020 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.