HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Plots
108 plots
Plot sizes
139–335 sq m
Land area
14,796 sq m
Road widening
5,667 sq mland set aside for road widening

Timeline

RERA approvedJan 2021
Proposed completionJan 2026
TodayJul 2026

Find your plot

Filed by type and size, in the batches the promoter registered — not a per-plot listing. Look yours up.

108 of 108 available
TypeArea sq mAvailable
Plot13914 of 14
Plot1412 of 2
Plot1421 of 1
Plot1442 of 2
Plot1452 of 2
Plot1462 of 2
Plot1472 of 2
Plot1482 of 2
Plot15313 of 13
Plot1611 of 1
Plot1671 of 1
Plot1711 of 1
Plot1721 of 1
Plot1842 of 2
Plot2291 of 1
Plot2612 of 2
Plot26654 of 54
Plot2741 of 1
Plot2761 of 1
Plot2811 of 1
Plot3121 of 1
Plot3351 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

RERA Telangana · Promoter registration

SADINENI MEGHANATH

IndividualPromoter type
Yadadri Bhuvanagiri, TelanganaBased in
2Projects
1City
2021–2026Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
194 plotson the public record across 2 projects
38,244 sq mplotted area
38,244 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
BUVANAGIRI
Mandal
Bhongir
District
Yadadri Bhuvanagiri
Pincode
508117
North boundary
NEIGHBOURS LAND
East boundary
NEIGHBOURS LAND
South boundary
NEIGHBOURS LAND
West boundary
NEIGHBOURS LAND
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 4.4km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 864 m · Gajwel Pragnapur RoadPrimary road 3.9 kmRailway line 2.9 kmNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 1.4 km · Somanath CheruvuRiver 1.4 km
distances only — not a flood assessment
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Hyderabad Metropolitan Development Authority (HMDA)

Urban Development Authority
Layout Permit no. 000029/LO/PlG/HMDA/Survey no. 54/P

The promised possession date (11 Jan 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 000029/LO/PlG/HMDA/ on the approving authority’s portal to confirm the sanction.

The approving body, at scale

HMDA

Urban Development Authority · Hyderabad metropolitan periphery

Has approved 3,643 RERA projectsabout 1 in 3 in Telangana.

an apartments market72% apartments · 28% plotted layouts. Layouts like yours are the smaller share here — this body mostly approves apartments.

Builders
2,462
On record
3,98,695 flats · 1,96,015 plots
Reach
71 mandals
Since
2016

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.