Complete project overview

RERA Telangana · Registration filing
Units
20 units
Unit mix
20 × 3BHK
Saleable area
96–110 sq mper unit, as filed
Floors
5
Land area
998 sq m
Built-up area
2,876 sq m

Timeline

RERA approvedApr 2020
Proposed completionApr 2026
TodayJul 2026
Construction progress

20% overall, as filed

Podiums0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Excavation100%
Basement & plinth100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

20 of 20 available
BuildingFloorTypeArea sq mAvailable
SR LILLY13BHK1001 of 1
SR LILLY13BHK961 of 1
SR LILLY13BHK1101 of 1
SR LILLY13BHK1051 of 1
SR LILLY23BHK1001 of 1
SR LILLY23BHKmortgaged961 of 1
SR LILLY23BHKmortgaged1101 of 1
SR LILLY23BHKmortgaged1051 of 1
SR LILLY33BHK1001 of 1
SR LILLY33BHK961 of 1
SR LILLY33BHK1101 of 1
SR LILLY33BHK1051 of 1
SR LILLY43BHK1001 of 1
SR LILLY43BHK961 of 1
SR LILLY43BHK1101 of 1
SR LILLY43BHK1051 of 1
SR LILLY53BHK1001 of 1
SR LILLY53BHK961 of 1
SR LILLY53BHK1101 of 1
SR LILLY53BHK1051 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

SRI DURGA BUILDERS & DEVELOPERS

PartnershipPromoter type
Nizamabad, TelanganaBased in
1Projects
1City
2020–2026Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
GANGASTHAN 1
Village
KANTESHWAR
Mandal
NIZAMABAD EAST (NEW)
District
Nizamabad
Pincode
503002
North boundary
ROAD
East boundary
HOUSE
South boundary
NEIGHBOUR PLOTS
West boundary
ROAD
What’s nearby
SchoolsNearest school 1.7km away
HealthcareHospital 1.1km away · Clinic within 2km
LifestyleNo parks within 2km · Swimming pool within 2km
ShoppingSupermarket 754m away · Mall 859m away
Getting around
Expressway 516 mPrimary road 2.9 kmRailway line 2.2 kmRailway station 2.8km away (Nizamabad Junction)Limited bus connectivity nearby
Water & environment
River 789 m · Phulang VaguWater body 3.9 km
distances only — not a flood assessment
Declared external development
Sewerage (Chamber,…80%
Water supply10%
Roads0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Directorate of Town & Country Planning (DTCP)

Town & Country Planning (DTCP)
Building Permit no. 3072/W1/2019/3814Survey no. 261/EE,261/E,266/A,266/AA,266/E

The promised possession date (1 Apr 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 3072/W1/2019/3814 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

DTCP

Town & Country Planning · towns & district HQs across Telangana

Has approved 3,737 RERA projectsabout 1 in 3 in Telangana, more than any other body in the state.

a plotted-layout market32% apartments · 68% plotted layouts. Apartments like yours are the smaller share here — this body mostly approves plotted layouts.

Builders
2,933
On record
41,686 flats · 4,33,404 plots
Reach
287 mandals
Since
2012

More layout-heavy than Telangana overall — 68% plots here vs 34% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.