HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
39 units
Unit mix
24 × 3BHK, 14 × 2BHK, 1 × 3bk
Saleable area
99–156 sq mper unit, as filed
Floors
5
Land area
2,158 sq m
Built-up area
6,426 sq m
Road widening
138 sq mland set aside for road widening

Timeline

RERA approvedOct 2021
Proposed completionOct 2024
TodayJul 2026
Construction progress

90% overall, as filed

Podiums0%
Excavation100%
Basement & plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

31 of 39 available
BuildingFloorTypeArea sq mAvailable
SRI OM TOWERS13BHK1561 of 1
SRI OM TOWERS12BHK1040 of 1
SRI OM TOWERS13BHK1510 of 1
SRI OM TOWERS13BHK1471 of 1
SRI OM TOWERS12BHK991 of 1
SRI OM TOWERS13bk1471 of 1
SRI OM TOWERS13BHK1451 of 1
SRI OM TOWERS23BHK1471 of 1
SRI OM TOWERS22BHKmortgaged991 of 1
SRI OM TOWERS23BHKmortgaged1471 of 1
SRI OM TOWERS23BHKmortgaged1451 of 1
SRI OM TOWERS22BHKmortgaged1451 of 1
SRI OM TOWERS23BHKmortgaged1511 of 1
SRI OM TOWERS22BHKmortgaged1041 of 1
SRI OM TOWERS23BHKmortgaged1561 of 1
SRI OM TOWERS33BHKmortgaged1471 of 1
SRI OM TOWERS32BHKmortgaged991 of 1
SRI OM TOWERS33BHK1471 of 1
SRI OM TOWERS32BHK1451 of 1
SRI OM TOWERS32BHK1041 of 1
SRI OM TOWERS33BHK1510 of 1
SRI OM TOWERS33BHK1560 of 1
SRI OM TOWERS33BHK1450 of 1
SRI OM TOWERS43BHK1472 of 2
SRI OM TOWERS43BHK1451 of 1
SRI OM TOWERS42BHK1451 of 1
SRI OM TOWERS43BHK1511 of 1
SRI OM TOWERS42BHK990 of 1
SRI OM TOWERS42BHK1040 of 1
SRI OM TOWERS43BHK1560 of 1
SRI OM TOWERS53BHK1472 of 2
SRI OM TOWERS52BHK991 of 1
SRI OM TOWERS53BHK1451 of 1
SRI OM TOWERS52BHK1451 of 1
SRI OM TOWERS53BHK1511 of 1
SRI OM TOWERS52BHK1041 of 1
SRI OM TOWERS53BHK1561 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

SRI OM BUILDERS

PartnershipPromoter type
Ranga Reddy, TelanganaBased in
3Projects
3Cities
2019–2025Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
84 homeson the public record across 3 projects
12,206 sq mbuilt-up filed
4,065 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Directorate of Town & Country Planning (DTCP)Town & Country Planning (DTCP)this project1 of 3 projects
Greater Hyderabad Municipal Corporation (GHMC)Municipal / Corporation1 of 3 projects
Hyderabad Metropolitan Development Authority (HMDA)Urban Development Authority1 of 3 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
DEVANPALLY
Mandal
Kamareddy
District
Kamareddy
Pincode
503111
North boundary
ROAD
East boundary
ROAD
South boundary
OPEN LAND OF NEIGHBOURS
West boundary
ROAD
What’s nearby
Schools1 school within 500m · 3 educational institutions within 1km · College or university 1.3km away
HealthcareHospital 78m away · 9 clinics within 1km · Doctor's clinic within 1km
LifestylePark 649m away · Gym or sports centre 410m away · 8 restaurants and cafes within 1km
ShoppingSupermarket 495m away · Mall 101m away · Bank 210m away
Getting around
Expressway 2.8 kmPrimary road 103 mRailway line 759 mRailway station 898m away (Kamareddi)Bus stop within 1km
Water & environment
Water body 3.3 km
distances only — not a flood assessment
Declared external development
Roads100%
Water supply100%
Sewerage (Chamber,…100%
Green Strip/TOT LO…100%
Street lighting100%
Fire safety100%
Electricity100%
Aggregate area of …100%
Rainwater0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Directorate of Town & Country Planning (DTCP)

Town & Country Planning (DTCP)
Building Permit
Survey no. 227/2B NEW 227/2A OLD

The promised possession date (27 Oct 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

DTCP

Town & Country Planning · towns & district HQs across Telangana

Has approved 3,737 RERA projectsabout 1 in 3 in Telangana, more than any other body in the state.

a plotted-layout market32% apartments · 68% plotted layouts. Apartments like yours are the smaller share here — this body mostly approves plotted layouts.

Builders
2,933
On record
41,686 flats · 4,33,404 plots
Reach
287 mandals
Since
2012

More layout-heavy than Telangana overall — 68% plots here vs 34% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.