HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
71 units
Unit mix
71 × Parking Slots
Saleable area
1823–1906 sq mper unit, as filed
Floors
7
Land area
3,081 sq m
Built-up area
13,624 sq m
Road widening
394 sq mland set aside for road widening

Timeline

RERA approvedJan 2022
Proposed completionJan 2024
TodayJul 2026
Construction progress

10% overall, as filed

Basement & plinth0%
Podiums0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Excavation100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

71 of 71 available
BuildingFloorTypeArea sq mAvailable
VARDHAN TOWERS1Parking Slots042 of 42
VARDHAN TOWERS2Parking Slots029 of 29

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

RERA Telangana · Promoter registration

SRI REDDY CONSTRUCTIONS

PartnershipPromoter type
Warangal Urban, TelanganaBased in
1Projects
1City
2022–2024Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
WARANGAL
Mandal
Hanamkonda
District
Warangal Urban
Pincode
506001
North boundary
LAND OF MRUTHYNJAYA RAO AND OTHERS
East boundary
LAND OF LAND OWNERS OWN PASSAGE
South boundary
150 FEET WIDE ROAD
West boundary
LAND OF LAND LORDS
What’s nearby
Schools1 school within 1km · 4 educational institutions within 1km · College or university 587m away
HealthcareHospital 396m away · 2 clinics within 1km · Pharmacy within 1km
LifestylePark 1.1km away · Gym or sports centre 1.4km away
ShoppingNo supermarket within 2km · Mall 975m away · Bank 912m away
Getting around
Expressway 737 mPrimary road 305 mRailway line 3.7 kmRailway station 4.5km away (Warangal)Limited bus connectivity nearby
Water & environment
River 403 mWater body 596 m
distances only — not a flood assessment
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Directorate of Town & Country Planning (DTCP)

Town & Country Planning (DTCP)
Building Permit no. 3006/31839/W30/2021Survey no. 571

The promised possession date (7 Jan 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 3006/31839/W30/2021 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

DTCP

Town & Country Planning · towns & district HQs across Telangana

Has approved 3,737 RERA projectsabout 1 in 3 in Telangana, more than any other body in the state.

a plotted-layout market32% apartments · 68% plotted layouts. Apartments like yours are the smaller share here — this body mostly approves plotted layouts.

Builders
2,933
On record
41,686 flats · 4,33,404 plots
Reach
287 mandals
Since
2012

More layout-heavy than Telangana overall — 68% plots here vs 34% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.