Complete project overview

RERA Telangana · Registration filing
Units
20 units
Unit mix
20 × 2BHK
Saleable area
92–102 sq mper unit, as filed
Floors
5
Land area
749 sq m
Built-up area
2,304 sq m

Timeline

RERA approvedMay 2019
Proposed completionMay 2025
TodayJul 2026
Construction progress

90% overall, as filed

Podiums0%
Excavation100%
Basement & plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

20 of 20 available
BuildingFloorTypeArea sq mAvailable
SRI SAI MANOHARA TOWERS12BHK923 of 3
SRI SAI MANOHARA TOWERS12BHK1021 of 1
SRI SAI MANOHARA TOWERS22BHKmortgaged923 of 3
SRI SAI MANOHARA TOWERS22BHKmortgaged1021 of 1
SRI SAI MANOHARA TOWERS32BHK923 of 3
SRI SAI MANOHARA TOWERS32BHK1021 of 1
SRI SAI MANOHARA TOWERS42BHK1001 of 1
SRI SAI MANOHARA TOWERS42BHK922 of 2
SRI SAI MANOHARA TOWERS42BHK1021 of 1
SRI SAI MANOHARA TOWERS52BHK923 of 3
SRI SAI MANOHARA TOWERS52BHK1021 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

SRI SAI CONSTRUCTIONS

PartnershipPromoter type
Karimnagar, TelanganaBased in
25Projects
16Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
622 homeson the public record across 25 projects
74,295 sq mbuilt-up filed
31,280 sq mland declared
₹102.52 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Greater Hyderabad Municipal Corporation (GHMC)Municipal / Corporation11 of 24 projects
Director, Town and Country PlanningTown & Country Planning (DTCP)5 of 24 projects
Directorate of Town & Country Planning (DTCP)Town & Country Planning (DTCP)this project3 of 24 projects
Hyderabad Metropolitan Development Authority (HMDA)Urban Development Authority2 of 24 projects
BBMP - Bruhat Bengaluru Mahanagara PalikeMunicipal / Corporation1 of 24 projects
Commissioner, APCRDAMunicipal / Corporation1 of 24 projects
Vice Chairman, UDAUrban Development Authority1 of 24 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
MARKANDEYA NAGAR
District
Karimnagar
Pincode
505001
North boundary
OTHERS LAND
East boundary
ROAD WIDTH 9
South boundary
VACANT LAND
West boundary
VACANT LAND
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 775m away · Clinic within 2km · Doctor's clinic within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km · Mall 1.8km away
Getting around
Expressway 2.2 kmPrimary road 279 m · Vemulawada BypassRailway line 3.9 kmRailway station 4.7km away (Karimnagar)Bus stop within 1km
Water & environment
Canal 2.0 km · SRSP Kakatiya Canal
distances only — not a flood assessment
Declared external development
Water supply100%
Sewerage (Chamber,…100%
Green Strip/TOT LO…100%
Rainwater100%
Electricity100%
Roads0%
Rainwater0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Renewable energy0%
Fire safety0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Directorate of Town & Country Planning (DTCP)

Town & Country Planning (DTCP)
Building Permit no. 3011/W33/2019/4720Survey no. 1047

The promised possession date (10 May 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 3011/W33/2019/4720 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

DTCP

Town & Country Planning · towns & district HQs across Telangana

Has approved 3,737 RERA projectsabout 1 in 3 in Telangana, more than any other body in the state.

a plotted-layout market32% apartments · 68% plotted layouts. Apartments like yours are the smaller share here — this body mostly approves plotted layouts.

Builders
2,933
On record
41,686 flats · 4,33,404 plots
Reach
287 mandals
Since
2012

More layout-heavy than Telangana overall — 68% plots here vs 34% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.