Complete project overview

RERA Telangana · Registration filing
Units
10 units
Unit mix
10 × 3BHK
Saleable area
132–134 sq mper unit, as filed
Floors
5
Land area
393 sq m
Built-up area
14,976 sq m

Timeline

RERA approvedJun 2023
Proposed completionJun 2026
TodayJul 2026
Construction progress

90% overall, as filed

Podiums0%
Excavation100%
Basement & plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

10 of 10 available
BuildingFloorTypeArea sq mAvailable
SUDHA HOMES13BHKmortgaged1341 of 1
SUDHA HOMES13BHKmortgaged1321 of 1
SUDHA HOMES23BHK1341 of 1
SUDHA HOMES23BHK1321 of 1
SUDHA HOMES33BHK1341 of 1
SUDHA HOMES33BHK1321 of 1
SUDHA HOMES43BHK1341 of 1
SUDHA HOMES43BHK1321 of 1
SUDHA HOMES53BHK1341 of 1
SUDHA HOMES53BHK1321 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

LIFESTYLE INFRACON LLP

LLPPromoter type
Hyderabad, TelanganaBased in
1Projects
1City
2023–2026Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Telangana · Registration filing
Locality
GANDIPET
Village
Narsingi
Mandal
Gandipet
District
Ranga Reddy
Pincode
500075
North boundary
VACANT LAND
East boundary
PLOT NO 14 PART OLD NO 532
South boundary
9 M WIDE ROAD
West boundary
PLOT NO 12 PART OLD NO 530 P
What’s nearby
SchoolsNo schools within 2km
HealthcareNo hospital within 5km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 886 mPrimary road 2.8 kmNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
River 1.8 km · Musi RiverWater body 2.0 km
distances only — not a flood assessment
Government land classification

No residential (House Sites) class on record. The state classes this village’s land as Dry land, Agricultural Land fit for H.S., Land abutting NH/SH/ZPP/MPP. If it’s sold as residential plots, verify the layout’s conversion / approval.

Telangana Registration & Stamps
Declared external development
Water supply100%
Sewerage (Chamber,…100%
Green Strip/TOT LO…100%
Rainwater100%
Electricity100%
Roads0%
Rainwater0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Renewable energy0%
Fire safety0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
Price analysisno declared cost on this filing — one government benchmark below

This state’s RERA filing carries no declared build cost at all — nothing to turn into a per-unit or per-sq-ft figure here. The one real, government-sourced number below is the closest thing to a benchmark this record can offer.

Government guidance value
₹47,600/sq ydresidential

₹56,929/sq m · effective May 2026 · apartments ₹6,600/sq ft, same source

The state’s minimum value for this locality’s land, set for stamp duty — a floor, not a market price. Source: Telangana Registration & Stamps.

04

Planning authority

RERA Telangana · Approved building plan

Hyderabad Metropolitan Development Authority (HMDA)

Urban Development Authority
Building Permit
Survey no. 300 TO 303, 306 TO 311 & 313 TO 315

The promised possession date (28 Jun 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

HMDA

Urban Development Authority · Hyderabad metropolitan periphery

Has approved 3,643 RERA projectsabout 1 in 3 in Telangana.

an apartments market72% apartments · 28% plotted layouts. Apartments like yours are this body's core business.

Builders
2,462
On record
3,98,695 flats · 1,96,015 plots
Reach
71 mandals
Since
2016

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.