Complete project overview

RAJ-RERA · Registration filing
Land area
1,374 sq m
Completion deadline extended
2 extensions on record — latest to 31 Mar 2022declared reason: force majeure
Description
The project consist of B+G+14 as per Approval Letter NNK/23948-51 from Nagar nigam kota and flat details as followed :-Total 32 Flats(3BHK -12 on 4th, 5th and 6th floors, 5BHK -18, on 1st, 2nd, 3rd, 7th, 8th, 9th, 10th, 11th,12th Floors And 2 Duplex on 13th and 14th Floors.),Parking has been filled as per total E. C. U. provided as per sanctioned Basement& ground floor plan.

Timeline

Construction startApr 2016
RERA registeredApr 2019
Proposed completionMar 2020
TodayJul 2026
02

Builder’s track record

RAJ-RERA · Promoter registration

PAARTH INFRAWORKS PVT LTD

OrganisationPromoter type
Kota, RajasthanBased in
1Projects
1City
2019–2020Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
PLOT NO.92, SHAKTI NAGAR,DUSHERA SCHEME, KOTA, Ladpura, Kota, 324001
Village
KOTA
Taluka
Ladpura
District
Kota
Pincode
324001
What’s nearby
SchoolsNearest school 1.9km away · College or university 1.4km away
HealthcareHospital 107m away · 3 clinics within 1km · Doctor's clinic within 1km
LifestylePark 1.6km away
ShoppingNo supermarket within 2km
Getting around
Expressway 4.6 km · Kota BypassPrimary road 376 m · Barrage RoadRailway line 1.4 kmRailway station 4.1km away (Dakaniya Talav)Limited bus connectivity nearby
Water & environment
River 647 mCanal 892 m
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹31.00 Cr declared. What that works out to:

14%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan
Building Permitapproved 12 Apr 2019 · 7 yrs ago

The promised possession date (31 Mar 2020) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.