HORIZONMarkets
01

Complete project overview

UP-RERA · Registration filing
Units
46 units
Unit mix
46 × 4 BHK
Carpet area
227–227 sq mper unit, as filed
Floors
11
Land area
10,058 sq m

Timeline

Project startedAug 2012
RERA registeredAug 2017
Proposed completionJun 2021
TodayJul 2026

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

46 units across 12 batches
BuildingFloorTypeArea sq mCount
ORB-R (PHASE III)GF4 BHK2272
ORB-R (PHASE III)14 BHK2274
ORB-R (PHASE III)24 BHK2274
ORB-R (PHASE III)34 BHK2274
ORB-R (PHASE III)44 BHK2274
ORB-R (PHASE III)54 BHK2274
ORB-R (PHASE III)64 BHK2274
ORB-R (PHASE III)74 BHK2274
ORB-R (PHASE III)84 BHK2274
ORB-R (PHASE III)94 BHK2274
ORB-R (PHASE III)104 BHK2274
ORB-R (PHASE III)114 BHK2274

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

UP-RERA · Promoter registration

SUPERTECH LIMITED

CompanyPromoter type
27Registered projects
28Projects
3Cities
2017–2022Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
24,145 homes · 760 plotson the public record across 28 projects
88,361 sq mplotted area
7,44,219 sq mland declared
₹6370.60 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

UP-RERA · Registration filing
District
Gautam Buddha Nagar
Tehsil
Gautam Buddha Nagar
Site access
As per master plan of Authority all access have developed by noida Authority and project is accessible
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.4km away · 2 clinics within 1km
Lifestyle2 parks within 500m · Gym or sports centre 1.3km away
ShoppingSupermarket 243m away · Mall 1.7km away
Getting around
Primary road 1.1 km · Sector 78 Main RoadMetro station 897m away (Rainbow Metro Station)Limited bus connectivity nearby
Water & environment
Water body 541 m · swimming poolCanal 1.3 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹217.98 Cr declared to build 46 flats. What that works out to:

₹4.74 Crdeclared cost per flatall-in — land + construction

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

UP-RERA · Approved building plan
approved 30 Sep 2014 · 11 yrs ago
Building Permit no. 2014/III-227/757

The promised possession date (30 Jun 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 2014/III-227/757 on the approving authority’s portal to confirm the sanction.

Complaints register

28 complaints on UP-RERA’s register for this project.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — UP-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.