As per Pt. No. 5 of Circular No. क्रमांक प.18(25)नविवि/सामान्य/2014 dated 27.06.2017 issued by Urban Development & Housing Department (Copy of the same attached under head “Project Approval Document” of “Documents Tab”) regarding Fire NOC, at the construction stage, instead of submitting Fire NOC, the promoter is only required to submit an Affidavit in this regard (Copy of the same attached under head “Project Approval Document” of “Documents Tab”).
As per the notification dated 14.09.2006 and 09.12.2016 respectively issued by Ministry of Environment, Forest and Climate Change, the projects having built up area of less than 20,000 sq. mtrs. are not required to obtain Environment Clearance and since the built up area of our project is less than 20,000 sq. mtrs., therefore, the requirement for Environment Clearance is not applicable on our project.
Also, NOC from Airport Authority of India is not required in this project.
Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.
Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Railway line 4.0 kmRailway station 4.5km away (Khatipura)Limited bus connectivity nearby
Water & environment
River 2.8 km · DhundWater body 3.4 km · Dravyavati RiverCanal 4.2 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price
₹27.20 Cr declared. What that works out to:
20%of the cost is land
This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.
Location & price analysis — done
04
Government Guidance Rate
Rajasthan registration department
In Rajasthan it’s called the DLC rate.
No government guidance rate is shown for this project.
Rajasthan's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.
That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.
Government Guidance Rate — done
05
Planning authority
RAJ-RERA · Approved building plan
Building Permitapproved 19 Feb 2018 · 8 yrs ago
The promised possession date (31 Oct 2020) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.
The occupancy certificate — the proof that isn’t here
An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.
Planning authority — done
06
Complaints & litigation
RAJ-RERA · public record
Complaints register
Not published. RAJ-RERA doesn’t publish a complaints register in the record Horizon reads.
So there is nothing to count here — which is not the same as nothing having been filed.
What the builder declared
Declared to RAJ-RERA
Litigation
None declared in this filing
Only what the builder declared, or what RAJ-RERA records itself, can appear here — a case filed elsewhere and never declared would not.
Not a verdict. A complaint can be dismissed and a case can be won; an order can be appealed.
Not a clean bill. An empty record means nothing was filed with RAJ-RERA, or that this register doesn’t publish it — never that nothing happened.
Complaints & litigation — done
07
Other projects nearby
The register · within 25 km
358 residential projects still under way within 25 km. Step out ring by ring: