Complete project overview

RAJ-RERA · Registration filing
Plots
142 plots
Land area
31,400 sq m
Completion deadline extended
2 extensions on record — latest to 31 Dec 2026declared reason: other than force majeure
Description
12.5% of the total saleable plots have been mortgaged by the Jaipur Development Authority against the internal development work of the project those plots are plot no. B-01 to B-04 & B-19 to B-21 (2237.99 Sq. Mtr.). Open Area of the project is 13420.21 sq. mtr. and the same is calculated by considering Park area as 1570 sq. mtrs., Facilities Area as 3140 sq. mtrs., M.T. as 20 sq. mtrs, S.W.M. Area as 50 sq. mtrs. and Road area as 8640.21 sq. mtrs.

Timeline

Construction startAug 2024
RERA registeredOct 2024
Proposed completionDec 2024
TodayJul 2026

Find your plot

Filed by type and size, in the batches the promoter registered — not a per-plot listing. Look yours up.

142 plots across 29 batches
TypeArea sq mCount
Plot5151
Plot4401
Plot4451
Plot4511
Plot1152
Plot4561
Plot4611
Plot5661
Plot1622
Plot11513
Plot10562
Plot1571
Plot14711
Plot5801
Plot4841
Plot1014
Plot1661
Plot1184
Plot1171
Plot1631
Plot1371
Plot4514
Plot3041
Plot701
Plot681
Plot616
Plot721
Plot685
Plot711

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each size exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RAJ-RERA · Promoter registration

UDAI GAJRAJ REAL ESTATE LLP

OrganisationPromoter type
Jaipur, RajasthanBased in
3Projects
1City
2024–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
272 plotson the public record across 3 projects
64,435 sq mplotted area
64,435 sq mland declared
₹19.26 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
772/136, 138, 137, 142, 143, 144, 774/145 & 166, Rampurawas Goner, Rampurawas Goner, Chaksu, Jaipur, 303903
Village
Rampurawas Goner
Taluka
Chaksu
District
Jaipur
Pincode
303903
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 301m away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 3.4 kmPrimary road 3 mRailway line 3.8 kmRailway station 3.8km away (Chaksu)Limited bus connectivity nearby
Price analysisdeclared build cost — not a sale price

₹7.64 Cr declared to build 142 plots. What that works out to:

₹5.38 Lakhdeclared cost per plotall-in — land + construction
₹226/sq ftof plotted area₹2,433/sq m
37%of the cost is land₹84/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan

Jaipur Development Authority

Development Authority
Layout Permitapproved 2 Oct 2024 · 1 yr ago

The promised possession date (31 Dec 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Jaipur Development Authority

Development authority

Has approved 644 RERA projectsabout 1 in 3 in Rajasthan, more than any other body in the state.

a mixed market52% apartments · 48% plotted layouts.

Builders
528
On record
15,937 flats · 30,970 plots
Reach
2 districts
Since
2017

More apartment-heavy than Rajasthan overall — 52% apartments here vs 34% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.