Complete project overview

RERA Assam · Registration filing
Registration category
ONGOINGnew vs ongoing at registration
Land area
1,473 sq m
Local land measure
1 BIGHA 0.5 KATHA 0 LECHA
RERA validity
5 Feb 2025
Completion
Occupancy / Completion Certificate on record

Timeline

RERA registeredFeb 2021
Proposed completionSep 2025
TodayJul 2026
02

Builder’s track record

RERA Assam · Promoter registration

TATVA INFRATECH

Firm/ Proprietorship FirmPromoter type
1Projects
1City
2021–2025Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Assam · Registration filing
District
KAMRUP METRO
Mouza / circle
DISPUR
Town / village
GUWAHATI
Site address
HOUSE NO. 27 - UPPER CHACHAL, RANAGA MATIR PATH, NEAR AMTOL PATH, BORMOTORIA, HENGRABARI, GUWAHATI
Pincode
781022
What’s nearby
SchoolsNearest school 1.1km away · College or university 1.6km away
HealthcareHospital 207m away · 8 clinics within 1km · Pharmacy within 500m
LifestylePark 1.0km away · Gym or sports centre 938m away · 9 restaurants and cafes within 1km
ShoppingSupermarket 214m away · Mall 268m away · Bank 287m away
Getting around
Expressway 2.0 km · NH37Primary road 208 m · Sixmile FlyoverRailway line 3.2 kmNo metro or railway within 5km2 bus stops within 500m
Water & environment
Water body 681 mRiver 1.5 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹6.50 Cr declared. What that works out to:

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Assam · Approved building plan

Guwahati Metropolitan Development Authority

Urban Development Authority
Building Permitapproved 21 Nov 2020 · 5 yrs ago

The promised possession date (22 Sep 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

Occupancy Certificate — the occupancy sign-off, on record

An Occupancy / Completion Certificateis on this project’s RERA Assam record — the completion / legal-to-occupy sign-off that most RERA records simply don’t carry. It is issued by the planning authority, not by RERA. Still confirm it covers your specific unit and block before you rely on it.

The approving body, at scale

Guwahati Metropolitan Development Authority

Development authority

Has approved 122 RERA projectsabout 1 in 7 in Assam.

an apartments market94% apartments · 6% plotted layouts. Apartments like yours are this body's core business.

Builders
112
On record
11,753 flats · 2,242 plots
Reach
2 districts
Since
2010

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Assam does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Assam does not publish a complaints register. This read cannot speak to them either way.