Complete project overview
RAJ-RERA · Registration filing- Units
- 718 units
- Mix
- 272 × 2 BHK · 233 × 1 BHK · 56 × 3 Bhk · 55 × EWS · 36 × LIG · 12 × Shop -GF-2,3,4,7,8,11 & FF-3,4,5,8,9,12
- Carpet area
- 24–574 sq mper-type range, as filed
- Land area
- 28,068 sq m
- Completion deadline extended
- 7 extensions on record — latest to 31 Mar 2026
- Description
- 1. Remark based on application received from promoter the company name has been read Terra Realcon Pvt. Ltd. instead Canopy Nirmans Pvt. Ltd. aforementioned promoter company has been merged with Terra Realcon Pvt. Ltd. with effect from 23.08.2017 Remarked 24.01.2018 2. Remark based on application received from promoter for change the project's Estimated Finish Date. The previous Estimated Finish Date was 31.03.2018. Remarked 11.07.2018As per remark the correct phase area has been rectified in Land Details of Registering Project.
Timeline
Find your flat
Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.
Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).
Builder’s track record
RAJ-RERA · Promoter registrationTerra Realcon Private Limited
Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.
Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Location & price analysis
RAJ-RERA · Registration filing- Address
- 576,586,587,588,589,590, Bhiwadi-Alwar Highway, Maseet, Tijara, Alwar, 301707
- Village
- Maseet
- Taluka
- Tijara
- District
- Alwar
- Pincode
- 301707
₹165.01 Cr declared to build 718 flats. What that works out to:
This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.
Planning authority
RAJ-RERA · Approved building planThe promised possession date (23 Oct 2018) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.
A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.
Bhiwadi Integrated Development Authority
Development authorityHas approved 59 RERA projects — 2.7% of Rajasthan.
an apartments market — 76% apartments · 24% plotted layouts. Apartments like yours are this body's core business.
- Builders
- 39
- On record
- 8,825 flats · 1,721 plots
- Since
- 2017
More apartment-heavy than Rajasthan overall — 76% apartments here vs 34% statewide.
Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.
What this record cannot tell you
- Build quality — no filing records how well it was actually built.
- Private disputes — only complaints escalated to the authority appear here.
- What it will be worth — the record is the past; it does not price the future.
- Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
- Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.