HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
109 units
Unit mix
55 × 3BHK, 49 × 2BHK, 1 × Multipurpose Hall, 1 × Baby Care Center, 1 × Spa Saloon, 1 × Gym, 1 × Indoor Games
Saleable area
101–189 sq mper unit, as filed
Floors
8
Buildings
4
Land area
7,669 sq m
Built-up area
23,599 sq m

Timeline

RERA approvedSep 2021
Proposed completionSep 2025
TodayJul 2026
Construction progress

63% overall, as filed

Flat fit-out0%
OC-readiness0%
Stairs & lifts40%
External finishes40%
Internal finishes50%
Excavation100%
Basement & plinth100%
Podiums100%
Stilt floor100%
Superstructure100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

109 of 109 available
BuildingFloorTypeArea sq mAvailable
ALPHA-BLOCK A13BHK1392 of 2
ALPHA-BLOCK A13BHK1072 of 2
ALPHA-BLOCK A13BHK1011 of 1
ALPHA-BLOCK A12BHK1421 of 1
ALPHA-BLOCK A12BHK1391 of 1
ALPHA-BLOCK A23BHK1411 of 1
ALPHA-BLOCK A23BHK1392 of 2
ALPHA-BLOCK A22BHK1012 of 2
ALPHA-BLOCK A22BHK1072 of 2
ALPHA-BLOCK A33BHKmortgaged1452 of 2
ALPHA-BLOCK A32BHKmortgaged1141 of 1
ALPHA-BLOCK A32BHKmortgaged1141 of 1
ALPHA-BLOCK A43BHK1561 of 1
ALPHA-BLOCK A43BHK1451 of 1
ALPHA-BLOCK A43BHK1891 of 1
ALPHA-BLOCK A42BHK1131 of 1
ALPHA-BLOCK A42BHK1141 of 1
ALPHA-BLOCK A53BHK1561 of 1
ALPHA-BLOCK A53BHK1451 of 1
ALPHA-BLOCK A52BHK1131 of 1
ALPHA-BLOCK A52BHK1141 of 1
ALPHA-BLOCK A52BHK1141 of 1
ALPHA-BLOCK A53BHK1452 of 2
ALPHA-BLOCK A63BHK1561 of 1
ALPHA-BLOCK A73BHK1561 of 1
BETA-BLOCK B13BHK1551 of 1
BETA-BLOCK B13BHK1211 of 1
BETA-BLOCK B12BHK1022 of 2
BETA-BLOCK B12BHK1072 of 2
BETA-BLOCK B22BHK1102 of 2
BETA-BLOCK B22BHK1021 of 1
BETA-BLOCK B22BHK1072 of 2
BETA-BLOCK B23BHK1261 of 1
BETA-BLOCK B22BHK1141 of 1
BETA-BLOCK B33BHKmortgaged1411 of 1
BETA-BLOCK B32BHKmortgaged1141 of 1
BETA-BLOCK B32BHKmortgaged1151 of 1
BETA-BLOCK B43BHK1691 of 1
BETA-BLOCK B43BHK1411 of 1
BETA-BLOCK B42BHK1151 of 1
BETA-BLOCK B42BHK1143 of 3
BETA-BLOCK B53BHK1691 of 1
BETA-BLOCK B53BHK1411 of 1
BETA-BLOCK B52BHK1141 of 1
BETA-BLOCK B52BHK1142 of 2
BETA-BLOCK B63BHK1691 of 1
BETA-BLOCK B63BHK1411 of 1
BETA-BLOCK B62BHK1141 of 1
BETA-BLOCK B62BHK1142 of 2
BETA-BLOCK B62BHK1151 of 1
BETA-BLOCK B73BHK1691 of 1
BETA-BLOCK B73BHK1411 of 1
BETA-BLOCK B72BHK1141 of 1
BETA-BLOCK B83BHK1691 of 1
BETA-BLOCK B83BHK1411 of 1
BETA-BLOCK B82BHK1141 of 1
CLUB HOUSE1Multipurpose Hall1801 of 1
CLUB HOUSE2Baby Care Center1801 of 1
CLUB HOUSE3Spa Saloonmortgaged1801 of 1
CLUB HOUSE4Gym1801 of 1
CLUB HOUSE5Indoor Games1801 of 1
GAMMA-BLOCK C13BHK1332 of 2
GAMMA-BLOCK C12BHK1121 of 1
GAMMA-BLOCK C22BHK1122 of 2
GAMMA-BLOCK C23BHK1332 of 2
GAMMA-BLOCK C33BHKmortgaged1471 of 1
GAMMA-BLOCK C33BHKmortgaged1481 of 1
GAMMA-BLOCK C33BHKmortgaged1471 of 1
GAMMA-BLOCK C43BHK1471 of 1
GAMMA-BLOCK C43BHK1481 of 1
GAMMA-BLOCK C42BHK1201 of 1
GAMMA-BLOCK C43BHK1471 of 1
GAMMA-BLOCK C43BHK1471 of 1
GAMMA-BLOCK C42BHK1211 of 1
GAMMA-BLOCK C53BHK1471 of 1
GAMMA-BLOCK C53BHK1481 of 1
GAMMA-BLOCK C52BHK1191 of 1
GAMMA-BLOCK C53BHK1471 of 1
GAMMA-BLOCK C53BHK1471 of 1
GAMMA-BLOCK C52BHK1211 of 1
GAMMA-BLOCK C63BHK1481 of 1
GAMMA-BLOCK C62BHK1191 of 1
GAMMA-BLOCK C63BHK1471 of 1
GAMMA-BLOCK C62BHK1471 of 1
GAMMA-BLOCK C63BHK1211 of 1
GAMMA-BLOCK C72BHK1191 of 1
GAMMA-BLOCK C73BHK1471 of 1
GAMMA-BLOCK C73BHK1471 of 1
GAMMA-BLOCK C82BHK1191 of 1
GAMMA-BLOCK C83BHK1471 of 1
GAMMA-BLOCK C83BHK1471 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

VEEKAY INFRASTRUCTURES

PartnershipPromoter type
Hyderabad, TelanganaBased in
1Projects
1City
2021–2025Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Telangana · Registration filing
Locality
MOKILA
Village
Mokila
Mandal
Shankarpalle
District
Ranga Reddy
Pincode
501203
North boundary
OTHER LAND
East boundary
OTHER LAND
South boundary
OTHER LAND
West boundary
ROAD WIDTH
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 4.0km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 524 m · Shankarpalli RoadRailway line 1.7 kmNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 1.6 km
distances only — not a flood assessment
Government land classification

No residential (House Sites) class on record. The state classes this village’s land as Dry land, Land abutting NH/SH/ZPP/MPP. If it’s sold as residential plots, verify the layout’s conversion / approval.

Telangana Registration & Stamps
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
Price analysisno declared cost on this filing — one government benchmark below

This state’s RERA filing carries no declared build cost at all — nothing to turn into a per-unit or per-sq-ft figure here. The one real, government-sourced number below is the closest thing to a benchmark this record can offer.

Government guidance value
₹4,600/sq ydresidential

₹5,502/sq m · effective May 2026 · apartments ₹2,700/sq ft, same source

The state’s minimum value for this locality’s land, set for stamp duty — a floor, not a market price. Source: Telangana Registration & Stamps.

04

Planning authority

RERA Telangana · Approved building plan

Hyderabad Metropolitan Development Authority (HMDA)

Urban Development Authority
Building Permit
Survey no. 112,112/A1,112/A2 & 112/A3

The promised possession date (21 Sep 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

HMDA

Urban Development Authority · Hyderabad metropolitan periphery

Has approved 3,643 RERA projectsabout 1 in 3 in Telangana.

an apartments market72% apartments · 28% plotted layouts. Apartments like yours are this body's core business.

Builders
2,462
On record
3,98,695 flats · 1,96,015 plots
Reach
71 mandals
Since
2016

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.