HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
112 units
Unit mix
100 × 4BHK, 11 × Commercial, 1 × Coomercial
Saleable area
619–1933 sq mper unit, as filed
Floors
25
Buildings
2
Land area
15,303 sq m
Built-up area
1,14,785 sq m
Road widening
634 sq mland set aside for road widening

Timeline

RERA approvedMay 2017
Proposed completionMay 2023
TodayJul 2026
Construction progress

54% overall, as filed

External finishes0%
OC-readiness0%
Flat fit-out20%
Stairs & lifts20%
Podiums50%
Stilt floor55%
Internal finishes60%
Excavation100%
Basement & plinth100%
Superstructure100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

30 of 112 available
BuildingFloorTypeArea sq mAvailable
BN TECH SQUARE1Commercialmortgaged1,9331 of 1
BN TECH SQUARE2Commercialmortgaged1,9331 of 1
BN TECH SQUARE3Coomercial1,9331 of 1
BN TECH SQUARE4Commercial1,9331 of 1
BN TECH SQUARE5Commercial1,9331 of 1
BN TECH SQUARE6Commercial1,9331 of 1
BN TECH SQUARE7Commercial1,9331 of 1
BN TECH SQUARE8Commercial1,9331 of 1
BN TECH SQUARE9Commercial1,9331 of 1
BN TECH SQUARE10Commercial1,9331 of 1
BN TECH SQUARE11Commercial1,9330 of 1
BN TECH SQUARE12Commercial1,9331 of 1
THE FIRST14BHKmortgaged6190 of 4
THE FIRST24BHKmortgaged6190 of 4
THE FIRST34BHKmortgaged6191 of 4
THE FIRST44BHKmortgaged6191 of 4
THE FIRST54BHK6190 of 1
THE FIRST54BHKmortgaged6191 of 3
THE FIRST64BHK6190 of 4
THE FIRST74BHK6190 of 4
THE FIRST84BHK6194 of 4
THE FIRST94BHK6191 of 4
THE FIRST104BHK6190 of 4
THE FIRST114BHK6191 of 4
THE FIRST124BHK6191 of 4
THE FIRST134BHK6191 of 4
THE FIRST144BHK6191 of 4
THE FIRST154BHK6190 of 4
THE FIRST164BHK6191 of 4
THE FIRST174BHK6190 of 4
THE FIRST184BHK6191 of 4
THE FIRST194BHK6190 of 4
THE FIRST204BHK6192 of 4
THE FIRST214BHK6191 of 4
THE FIRST224BHK6191 of 4
THE FIRST234BHK6190 of 4
THE FIRST244BHK6191 of 4
THE FIRST254BHK6190 of 4

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

DSR BUILDERS AND DEVELOPERS

PartnershipPromoter type
Hyderabad, TelanganaBased in
3Projects
1City
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
210 homeson the public record across 3 projects
1,76,399 sq mbuilt-up filed
23,416 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
RAIDURG
Village
Pan Maktha
Mandal
Serilingampally
District
Ranga Reddy
Pincode
500081
North boundary
MAIN ROAD
East boundary
PART OF SURVEY NO 66-2
South boundary
LAND OF ROAD MYSTRY COLLEGE
West boundary
PART OF SURVEY NO 66-2
What’s nearby
Schools1 school within 500m · 5 educational institutions within 1km · College or university 761m away
HealthcareHospital 1.2km away · Pharmacy within 500m
LifestyleNo parks within 2km · 4 restaurants and cafes within 1km
ShoppingSupermarket 1.5km away · Convenience store within 500m
Getting around
Expressway 2.5 kmPrimary road 15 m · Bollaram RoadRailway line 3.8 kmMetro station 3.1km away (miyapur metro)Bus stop within 1km
Water & environment
Water body 629 m · Kandi Kunta
distances only — not a flood assessment
Declared external development
Rainwater50%
Community Building…50%
Fire safety50%
Water supply35%
Sewerage (Chamber,…35%
Electricity5%
Roads0%
Green Strip/TOT LO…0%
Street lighting0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit
Survey no. 66/2

The promised possession date (8 May 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.