RERA Karnataka · Registration filing
Status
Ongoing
Plots
99 plots
Land parcels
1 survey no

Timeline

Project startedOct 2025
RERA registeredMar 2026
Proposed completionDec 2031
TodayJul 2026
Construction progress

5% overall, as filed

From the promoter's latest quarterly progress report filed with RERA Karnataka — % complete overall and by stage, as of that filing. A dated snapshot, not a live tracker.

Find your plot

Every plot the builder registered, with the carpet area they filed. Look yours up and check it against what you were shown.

UnitTypeTotal sq m
1Plot125.32
2Plot111.42
3Plot111.42
4Plot111.42
5Plot111.42
6Plot111.42
7Plot111.42
8Plot111.42
9Plot111.42
10Plot111.42
11Plot111.42
12Plot111.42
13Plot111.42
14Plot111.42
15Plot111.42
16Plot111.42
17Plot111.42
18Plot111.42
19Plot111.42
20Plot111.42
21Plot111.42
22Plot111.42
23Plot111.42
24Plot111.42
25Plot111.42
26Plot111.42
27Plot111.42
28Plot111.42
29Plot111.42
30Plot111.42
31Plot111.42
32Plot111.42
33Plot111.42
34Plot111.42
35Plot111.42
36Plot111.42
37Plot111.42
38Plot111.42
39Plot111.42
40Plot111.42
41Plot111.42
42Plot111.42
43Plot111.42
44Plot111.42
45Plot111.42
46Plot111.42
47Plot111.42
48Plot78.01
49Plot78.90
50Plot91.26
51Plot81.11
52Plot84.29
53Plot87.91
54Plot91.52
55Plot95.13
56Plot98.75
57Plot102.36
58Plot105.98
59Plot113.91
60Plot73.23
61Plot67.56
62Plot97.32
63Plot111.42
64Plot111.42
65Plot138.94
66Plot207.41
67Plot139.29
68Plot111.42
69Plot79.23
70Plot95.87
71Plot126.90
72Plot111.42
73Plot111.42
74Plot107.36
75Plot101.20
76Plot111.42
77Plot111.42
78Plot108.41
79Plot123.60
80Plot111.42
81Plot111.42
82Plot124.99
83Plot120.81
84Plot111.42
85Plot111.42
86Plot118.42
87Plot105.61
88Plot111.42
89Plot106.73
90Plot108.09
91Plot109.61
92Plot111.11
93Plot112.62
94Plot114.13
95Plot115.64
96Plot117.15
97Plot118.66
98Plot120.17
99Plot91.59

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion.

02

Builder’s track record

RERA Karnataka · Promoter registration

KADIRI VENKATA NARASIMHA REDDY

ProprietorshipPromoter type
Bengaluru UrbanBased in
1Projects
1City
2026–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Karnataka · Registration filing
Taluk
Devanahalli
District
Bengaluru Rural
Pincode
562135
Address
SY NO: 21/1, VARADENAHALLI VILLAGE , CHANNARAYAPATTANA HOBLI , Devanahalli , Bengaluru Rural, Karnataka - 562135
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 3.5km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 3.3 km · Satellite Town Ring RoadPrimary road 3.3 km · Old Dabaspete - Hosur HighwayNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 480 mRiver 633 m · Dakshina Pinakini
distances only — not a flood assessment
Land, title & encumbrance
LandOwned by the promoter
ConversionConverted to non-agricultural
LitigationDeclared free of litigation
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
Price analysisdeclared build cost — not a sale price

₹15.00 Cr declared to build 99 plots. What that works out to:

₹15.15 Lakhdeclared cost per plotall-in — land + construction
67%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Karnataka · Approved building plan

BIAPPA - Bangalore Airport Area Planning Authority

Urban Development Authority
approved 4 Dec 2025 · 7 mo ago
Layout Permit no. BIAAPA/TP/LAO/99/2025-26Survey no. 21/1
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan BIAAPA/TP/LAO/99/2025-26 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

BIAPPA

Urban Development Authority · Bangalore Airport Area Planning Authority

Has approved 328 RERA projects3.8% of Karnataka.

a plotted-layout market30% apartments · 70% plotted layouts. Your plotted layout is this body's core business.

Builders
236
On record
20,448 flats · 19,692 plots
Reach
8 taluks
Since
2017

More layout-heavy than Karnataka overall — 70% plots here vs 38% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Complaints register

None on record with RERA Karnataka against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.