HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
58 units
Unit mix
1 × A005, 1 × B001, 1 × B002, 1 × B003, 1 × B005, 1 × A003, 1 × A004, 1 × B004, 1 × A102, 1 × A103, 1 × A105, 1 × B101, 1 × B102, 1 × B103, 1 × B105, 1 × A101, 1 × A104, 1 × B104, 1 × A202 Mortgage, 1 × A203 Mortgage, 1 × A205, 1 × B205, 1 × A201 Mortgage, 1 × B204, 1 × A204 Mortgage, 1 × B201 Mortgage, 1 × B202 Mortgage, 1 × B203 Mortgage, 1 × A302, 1 × A305, 1 × B301, 1 × B302, 1 × B303, 1 × B305, 1 × A303, 1 × A304, 1 × B304, 1 × A301, 1 × A402, 1 × A405, 1 × B401, 1 × B402, 1 × B403, 1 × B405, 1 × A403, 1 × A404, 1 × B404, 1 × A401, 1 × A502, 1 × A505, 1 × B501, 1 × B502, 1 × B503, 1 × B505, 1 × A501, 1 × A503, 1 × A504, 1 × B504
Saleable area
143–181 sq mper unit, as filed
Floors
6
Land area
3,567 sq m
Built-up area
8,906 sq m

Timeline

RERA approvedAug 2019
Proposed completionMar 2023
TodayJul 2026
Construction progress

15% overall, as filed

Podiums0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Stilt floor20%
Basement & plinth30%
Excavation100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

58 of 58 available
BuildingFloorTypeArea sq mAvailable
The Park Side1A0051741 of 1
The Park Side1B0011611 of 1
The Park Side1B0021571 of 1
The Park Side1B0031571 of 1
The Park Side1B0051681 of 1
The Park Side1A0031691 of 1
The Park Side1A0041431 of 1
The Park Side1B0041431 of 1
The Park Side2A1021621 of 1
The Park Side2A1031771 of 1
The Park Side2A1051811 of 1
The Park Side2B1011641 of 1
The Park Side2B1021571 of 1
The Park Side2B1031571 of 1
The Park Side2B1051681 of 1
The Park Side2A1011501 of 1
The Park Side2A1041431 of 1
The Park Side2B1041431 of 1
The Park Side3A202 Mortgagemortgaged1621 of 1
The Park Side3A203 Mortgagemortgaged1771 of 1
The Park Side3A2051811 of 1
The Park Side3B2051681 of 1
The Park Side3A201 Mortgagemortgaged1501 of 1
The Park Side3B2041431 of 1
The Park Side3A204 Mortgagemortgaged1431 of 1
The Park Side3B201 Mortgagemortgaged1641 of 1
The Park Side3B202 Mortgagemortgaged1571 of 1
The Park Side3B203 Mortgagemortgaged1571 of 1
The Park Side4A3021621 of 1
The Park Side4A3051811 of 1
The Park Side4B3011611 of 1
The Park Side4B3021571 of 1
The Park Side4B3031571 of 1
The Park Side4B3051681 of 1
The Park Side4A3031691 of 1
The Park Side4A3041431 of 1
The Park Side4B3041431 of 1
The Park Side4A3011501 of 1
The Park Side5A4021571 of 1
The Park Side5A4051741 of 1
The Park Side5B4011611 of 1
The Park Side5B4021571 of 1
The Park Side5B4031571 of 1
The Park Side5B4051681 of 1
The Park Side5A4031691 of 1
The Park Side5A4041431 of 1
The Park Side5B4041431 of 1
The Park Side5A4011501 of 1
The Park Side6A5021571 of 1
The Park Side6A5051741 of 1
The Park Side6B5011611 of 1
The Park Side6B5021571 of 1
The Park Side6B5031571 of 1
The Park Side6B5051681 of 1
The Park Side6A5011501 of 1
The Park Side6A5031691 of 1
The Park Side6A5041431 of 1
The Park Side6B5041431 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

Four Leaf Clover Projects LLP

LLPPromoter type
Hyderabad, TelanganaBased in
1Projects
1City
2019–2023Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
Gundla Pochampally
Mandal
Medchal
District
Medchal-Malkajgiri
Pincode
500100
North boundary
40 Ft Road
East boundary
122 and 139
South boundary
60 Ft Road
West boundary
50 Ft Road
What’s nearby
SchoolsNearest school 1.8km away
HealthcareHospital 1.7km away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingSupermarket 1.7km away · Mall 1.7km away
Getting around
Expressway 2.8 kmPrimary road 1.6 km · Jeedimetla Main RoadRailway line 3.9 kmRailway station 4.7km away (Suchitra Centre)Limited bus connectivity nearby
Water & environment
Water body 1.1 km · Fox SagarCanal 1.4 km
distances only — not a flood assessment
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Hyderabad Metropolitan Development Authority (HMDA)

Urban Development Authority
Building Permit no. 017457/MED/R1/U6/HMDSurvey no. 393(p), 394(p), and 395

The promised possession date (31 Mar 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 017457/MED/R1/U6/HMD on the approving authority’s portal to confirm the sanction.

The approving body, at scale

HMDA

Urban Development Authority · Hyderabad metropolitan periphery

Has approved 3,643 RERA projectsabout 1 in 3 in Telangana.

an apartments market72% apartments · 28% plotted layouts. Apartments like yours are this body's core business.

Builders
2,462
On record
3,98,695 flats · 1,96,015 plots
Reach
71 mandals
Since
2016

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.