01

Complete project overview

RERA Telangana · Registration filing
Units
15 units
Unit mix
15 × 3BHK
Saleable area
132–158 sq mper unit, as filed
Floors
5
Land area
748 sq m
Built-up area
1,849 sq m

Timeline

RERA approvedJun 2020
Proposed completionJan 2023
TodayJul 2026
Construction progress

49% overall, as filed

Podiums0%
Flat fit-out0%
OC-readiness10%
External finishes30%
Stairs & lifts40%
Internal finishes50%
Superstructure60%
Excavation100%
Basement & plinth100%
Stilt floor100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

15 of 15 available
BuildingFloorTypeArea sq mAvailable
THE RETREAT13BHKmortgaged1321 of 1
THE RETREAT13BHKmortgaged1581 of 1
THE RETREAT13BHK1491 of 1
THE RETREAT23BHK1581 of 1
THE RETREAT23BHK1491 of 1
THE RETREAT23BHK1321 of 1
THE RETREAT33BHK1581 of 1
THE RETREAT33BHK1491 of 1
THE RETREAT33BHK1321 of 1
THE RETREAT43BHK1581 of 1
THE RETREAT43BHK1491 of 1
THE RETREAT43BHK1321 of 1
THE RETREAT53BHK1581 of 1
THE RETREAT53BHK1491 of 1
THE RETREAT53BHK1321 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

Putty Developers

PartnershipPromoter type
Ranga Reddy, TelanganaBased in
4Projects
3Cities
2020–2024Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
55 homeson the public record across 4 projects
7,011 sq mbuilt-up filed
2,476 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Greater Hyderabad Municipal Corporation (GHMC)Municipal / Corporation2 of 4 projects
Hyderabad Metropolitan Development Authority (HMDA)Urban Development Authoritythis project2 of 4 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
NARSINGI
Village
Rajendra nagar
Mandal
Rajendranagar
District
Ranga Reddy
Pincode
500089
North boundary
PLOT NO L 9 L 10
East boundary
PLOT NO L 7
South boundary
PLOT NO 12
West boundary
ROAD WIDTH 12
What’s nearby
SchoolsNo schools within 2km · 6 educational institutions within 1km · College or university 71m away
HealthcareHospital 194m away
LifestylePark 1.9km away · Gym or sports centre 767m away
ShoppingNo supermarket within 2km · Bank 389m away · ATM within 500m
Getting around
Expressway 2.5 km · FlyoverPrimary road 10 m · Rajendra nagar roadRailway line 2.8 kmRailway station 2.8km away (Budvel)Bus stop within 500m
Water & environment
Water body 1.0 km
distances only — not a flood assessment
Declared external development
Rainwater50%
Electricity20%
Green Strip/TOT LO…10%
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Renewable energy0%
Fire safety0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Hyderabad Metropolitan Development Authority (HMDA)

Urban Development Authority
Building Permit
Survey no. 90

The promised possession date (31 Jan 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

HMDA

Urban Development Authority · Hyderabad metropolitan periphery

Has approved 3,643 RERA projectsabout 1 in 3 in Telangana.

an apartments market72% apartments · 28% plotted layouts. Apartments like yours are this body's core business.

Builders
2,462
On record
3,98,695 flats · 1,96,015 plots
Reach
71 mandals
Since
2016

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.