1) Plot No. 14,15,16,17,18,19,20,21,22,23,24,25 having Total Area 851.69Sq.Mtr are Mortgage with JDA for internal development. These Plots would be release after development work is completed and development charges are deposited with JDA.
2) Total of 12 plots have been included under 'Proposed but Not Sanctioned Number of Apartments/Plots,' which comprises plots mortgaged for internal development. 3) Open Area Total of 4519.95 Sq. Mtr. includes Park (869.92 Sq. Mtr), SWM(50 Sq. Mtr),MT(10 Sq.Mtr) PU(10.00 Sq.Mtr), and Road (3580.03 Sq. Mtr).
Timeline
Construction startMay 2025
RERA registeredJun 2025
Proposed completionAug 2026
TodaySep 2026
Find your plot
Filed by type and size, in the batches the builder registered — not a per-plot listing. Look yours up.
73 plots across 40 batches
TypeArea sq mCount
Plot701
Plot671
Plot751
Plot621
Plot681
Plot711
Plot721
Plot731
Plot744
Plot846
Plot1121
Plot1111
Plot1061
Plot1851
Plot861
Plot741
Plot741
Plot751
Plot761
Plot891
Plot761
Plot891
Plot1361
Plot8413
Plot921
Plot1362
Plot8413
Plot961
Plot1001
Plot1361
Plot1121
Plot971
Plot971
Plot1041
Plot1041
Plot1111
Plot1211
Plot1271
Plot1761
Plot2261
Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each size exist, not how many are still unsold (this state's filing carries no booking count).
573 homes · 73 plotson the public record across 5 projects
29,550 sq mbuilt-up filed
11,300 sq mplotted area
20,033 sq mland declared
₹20.68 Crdeclared build cost
Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.
Planning authoritiesthis builder's portfolio, by approving body
Jaipur Development AuthorityDevelopment Authoritythis project1 of 5 projects
Nagar Rachna Aani Mulya Nirdharan Vibhag Thane1 of 5 projects
Office Of District Collector ,ThaneCollector office1 of 5 projects
Vadodara Municipal CorporationMunicipal / Corporation1 of 5 projects
Vapi MunicipalityMunicipal / Corporation1 of 5 projects
Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.
Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Schools2 schools within 1km · 4 educational institutions within 1km
HealthcareHospital 249m away · 5 clinics within 1km · Pharmacy within 1km
LifestylePark 630m away · 22+ restaurants and cafes within 1km
ShoppingSupermarket 1.2km away · Convenience store within 1km · Bank 852m away
Getting around
Expressway 227 m · Acharya Shri Tulsi SetuPrimary road 1.1 kmRailway line 279 mMetro station 620m away (Civil Lines)4 bus stops within 500m
Water & environment
Canal 1.0 km · Kartar Pura Nala
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price
₹8.49 Cr declared to build 73 plots. What that works out to:
₹11.63 Lakhdeclared cost per plotall-in — land + construction
₹698/sq ftof plotted area₹7,512/sq m
58%of the cost is land₹404/sq ft of land
This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.
Location & price analysis — done
04
Government Guidance Rate
Rajasthan IGRS — DLC rates
In Rajasthan it’s called the DLC rate.
₹13,545per sq yd
₹16,200per sq m
Which rate
residential, interior plot
Matched to
The rate published for the village of “MADRAMPURA”.
Highest rate
₹19,565 per sq yd — the top road-facing rate among the 4 residential rates published for this village
By the road it faces
interior plot
₹16,200 / sq m
₹13,545 / sq yd
road-facing
₹14,700 / sq m
₹12,291 / sq yd
41–60 ft road
₹21,450 / sq m
₹17,935 / sq yd
61–99 ft road
₹22,430 / sq m
₹18,754 / sq yd
100 ft+ road
₹23,400 / sq m
₹19,565 / sq yd
The same land, priced by the width of the road it faces — each band the middle of the residential rates published for this village.
This filing declares ₹7,512 per sq m of plotted area — 0.46× the government figure. Declared cost is land and construction; the government guidance rate is what the state will not register a sale below. Neither is a sale price.
What this number is — and isn’t
The minimum value Rajasthan’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
Not a market price. Sales normally register above it, and how far above varies by place and by project.
Its fit depends on the grain the state publishes at. This one is matched at the level of village, and says so above. How Horizon decides what to show.
Government Guidance Rate — done
05
Planning authority
RAJ-RERA · Approved building plan
Jaipur Development Authority
Development Authority
Layout Permitapproved 5 Jun 2025 · 1 yr ago
The promised possession date (31 Aug 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.
The occupancy certificate — the proof that isn’t here
An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.
The approving body, at scale
Jaipur Development Authority
Development authority
Has approved 644 RERA projects — about 1 in 3 in Rajasthan, more than any other body in the state.
a mixed market — 52% apartments · 48% plotted layouts.
Builders
528
On record
15,937 flats · 30,970 plots
Reach
2 districts
Since
2017
More apartment-heavy than Rajasthan overall — 52% apartments here vs 34% statewide.
Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.