HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
18 units
Unit mix
1 × 102e, 1 × 101e, 1 × 103w, 1 × 201e, 1 × 202e, 1 × 203w, 1 × 302emortgage, 1 × 303wmortgage, 1 × 301e, 1 × 401e, 1 × 402e, 1 × 403w, 1 × 501e, 1 × 502e, 1 × 503w, 1 × 603w, 1 × 601e, 1 × 602e
Saleable area
268–293 sq mper unit, as filed
Floors
6
Land area
1,635 sq m
Built-up area
4,572 sq m

Timeline

RERA approvedSep 2018
Proposed completionDec 2021
TodayJul 2026
Construction progress

96.5% overall, as filed

Flat fit-out90%
OC-readiness90%
Internal finishes95%
Stairs & lifts95%
External finishes95%
Excavation100%
Basement & plinth100%
Podiums100%
Stilt floor100%
Superstructure100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

4 of 18 available
BuildingFloorTypeArea sq mAvailable
Block A1102e2931 of 1
Block A1101e2680 of 1
Block A1103w2800 of 1
Block A2201e2681 of 1
Block A2202e2930 of 1
Block A2203w2800 of 1
Block A3302emortgagemortgaged2931 of 1
Block A3303wmortgagemortgaged2801 of 1
Block A3301e2680 of 1
Block A4401emortgaged2680 of 1
Block A4402e2930 of 1
Block A4403w2800 of 1
Block A5501e2680 of 1
Block A5502e2930 of 1
Block A5503w2800 of 1
Block A6603w2800 of 1
Block A6601e2680 of 1
Block A6602e2930 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

Sri Srinivasa Constructions

PartnershipPromoter type
Hyderabad, TelanganaBased in
14Projects
7Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
638 homeson the public record across 14 projects
93,114 sq mbuilt-up filed
50,281 sq mland declared
₹19.95 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Director, Town and Country PlanningTown & Country Planning (DTCP)5 of 14 projects
Greater Hyderabad Municipal Corporation (GHMC)Municipal / Corporationthis project4 of 14 projects
Hyderabad Metropolitan Development Authority (HMDA)Urban Development Authority4 of 14 projects
Commissioner, ULBMunicipal / Corporation1 of 14 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
Rajendra Nagar
District
Hyderabad
Pincode
500030
North boundary
50 ft ROAD
East boundary
Plot no 178
South boundary
Plot no 202 and 203
West boundary
40 Ft ROAD
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 2.3km away
LifestylePark 855m away
ShoppingNo supermarket within 2km
Getting around
Expressway 4.2 km · Chavella roadPrimary road 912 m · Rajendra nagar roadRailway line 4.6 kmRailway station 4.7km away (Budvel)Limited bus connectivity nearby
Water & environment
Water body 1.2 km · Patthikunta tankRiver 1.6 km · Esi River
distances only — not a flood assessment
Declared external development
Rainwater100%
Water supply90%
Green Strip/TOT LO…90%
Rainwater90%
Fire safety50%
Aggregate area of …50%
Sewerage (Chamber,…25%
Sewage25%
Solid waste25%
Roads0%
Street lighting0%
Community Building…0%
Renewable energy0%
Electricity0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit no. 1/C11/15286/2018Survey no. 308/PART

The promised possession date (31 Dec 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 1/C11/15286/2018 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.