7 on filequarterly progress reports filed with RERA
Timeline
RERA registeredJun 2019
Proposed completionOct 2020
TodaySep 2026
Construction progress
100% overall, as filed
Internal Roads And Footpaths100%
Water Supply100%
Street Lighting100%
Electric Meter Room,Sub Station,Recieving Statiom100%
Open Parking100%
Boundary Wall100%
Security Service100%
Drainage100%
From the builder's latest quarterly progress report filed with RERA Chhattisgarh — % complete overall and per infrastructure work, as of that filing. A dated snapshot, not a live tracker.
The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Builder's track record — done
03
Location & price analysis
RERA Chhattisgarh · Registration filing
District
Janjgir-Champa
Tehsil
Janjgir
Address
WARD NO .10 JANJGIR TEHSIL- JANJGIR DIST.JANJGIR
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 2.5km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 2.4 km · NH49Primary road 2.3 kmRailway line 1.4 kmRailway station 1.6km away (Janjgir Naila)Limited bus connectivity nearby
Water & environment
Water body 654 mCanal 2.0 kmRiver 4.5 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price
₹48.04 Lakh declared. What that works out to:
11%of the cost is land
This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.
Location & price analysis — done
04
Government Guidance Rate
Chhattisgarh registration department
In Chhattisgarh it’s called the collector guideline rate.
No government guidance rate is shown for this project.
Chhattisgarh's government guidance rates aren't in Horizon's record yet.
That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.
Government Guidance Rate — done
05
Complaints & litigation
RERA Chhattisgarh · public record
Complaints, as the builder reports them
None in the builder’s latest quarterly return to RERA Chhattisgarh.
The builder’s own count of grievances it received — not RERA Chhattisgarh’s register, which isn’t published. Cases the builder declares are listed below.
What the builder declared
Declared to RERA Chhattisgarh
Litigation
None declared in this filing
Only what the builder declared, or what RERA Chhattisgarh records itself, can appear here — a case filed elsewhere and never declared would not.
Not a verdict. A complaint can be dismissed and a case can be won; an order can be appealed.
Not a clean bill. An empty record means nothing was filed with RERA Chhattisgarh, or that this register doesn’t publish it — never that nothing happened.
Complaints & litigation — done
06
Other projects nearby
The register · within 25 km
8 plotted projects still under way within 25 km. Step out ring by ring:
Of the 19 projects the radar draws within 6 km — every kind, every stage — 1 is a plotted project still under way. This list keeps only those, and looks further out.