Complete project overview

RAJ-RERA · Registration filing
Land area
1,231 sq m
Completion deadline extended
2 extensions on record — latest to 31 Dec 2021declared reason: other than force majeure
Description
Maps for the project was approves on 22.10.2013 and got revised on 13.06.2016. As on date approval on 13.06.2016 stands valid. Both approval and maps attached for refrence

Timeline

RERA registeredOct 2017
Proposed completionDec 2017
TodayJul 2026
02

Builder’s track record

RAJ-RERA · Promoter registration

GOVERDHAN LAL TAK

IndividualPromoter type
Udaipur, RajasthanBased in
3Projects
1City
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
20 homeson the public record across 3 projects
11,476 sq mbuilt-up filed
3,411 sq mland declared
₹40.77 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Municipal CorporationMunicipal Corporationthis project1 of 2 projects
Udaipur Development AuthorityDevelopment Authority1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
PLOT NO. 34 B NEW FATEHPURA UDAIPUR, NEW FATEHPURA, UDAIPUR, Girwa, Udaipur, 313001
Village
UDAIPUR
Taluka
Girwa
District
Udaipur
Pincode
313001
What’s nearby
SchoolsNearest school 1.9km away · College or university 1.3km away
HealthcareHospital 81m away · 1 clinic within 1km
LifestyleNo parks within 2km · 14+ restaurants and cafes within 1km
ShoppingSupermarket 171m away · Mall 999m away · Bank 404m away
Getting around
Expressway 954 m · Laxmi Vilas RoadPrimary road 274 m · Sukadia CircleRailway line 3.0 kmRailway station 3.8km away (Udaipur City)Bus stop within 1km
Water & environment
River 226 m
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹8.03 Cr declared. What that works out to:

49%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan

Municipal Corporation

Municipal Corporation
Building Permitapproved 16 Oct 2017 · 8 yrs ago

The promised possession date (31 Dec 2017) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal body

A Nagar Nigam / Parishad / Palika that sanctions within its own town limits. It has approved 358 RERA projects across 29 districts about 1 in 6 in Rajasthan.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.