HORIZONMarkets
01

Complete project overview

RAJ-RERA · Registration filing
Land area
4,85,391 sq m
Description
This scheme reduce traffic conjunction in jodhpur city.

Timeline

Construction startApr 2020
RERA registeredAug 2020
Proposed completionDec 2021
TodayJul 2026
02

Builder’s track record

RAJ-RERA · Promoter registration

JODHPUR DEVELOPMENT AUTHORITY

OrganisationPromoter type
Jodhpur, RajasthanBased in
23Projects
1City
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
6,802 homes · 10,164 plotson the public record across 23 projects
4,84,589 sq mbuilt-up filed
1,45,02,293 sq mplotted area
1,48,93,750 sq mland declared
₹1797.44 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
Khasra No 142, 295, Mogra Khurd, Mogra Khurd, Luni, Jodhpur, 342802
Village
Mogra Khurd
Taluka
Luni
District
Jodhpur
Pincode
342802
What’s nearby
SchoolsNo schools within 2km
HealthcareNo hospital within 5km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 321 mPrimary road 1.8 kmNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 3.3 kmRiver 4.8 km · Luni
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹144.21 Cr declared. What that works out to:

₹276/sq ftof plotted area₹2,971/sq m
65%of the cost is land₹181/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan

Jodhpur Development Authority

Development Authority
Layout Permitapproved 4 Aug 2020 · 5 yrs ago

The promised possession date (25 Dec 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Jodhpur Development Authority

Development authority

Has approved 180 RERA projectsabout 1 in 12 in Rajasthan.

a plotted-layout market12% apartments · 88% plotted layouts. Your plotted layout is this body's core business.

Builders
149
On record
853 flats · 17,456 plots
Reach
3 districts
Since
2017

More layout-heavy than Rajasthan overall — 88% plots here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.