Complete project overview

RAJ-RERA · Registration filing
Land area
12,240 sq m
Completion deadline extended
1 extension on record — latest to 31 Oct 2018declared reason: other than force majeure
Description
As per UIT Kota letter dt. 28-01-2016 as of now the project have been approved for lower basement, upper basement, stilt and eight floors as on date

Timeline

Construction startJun 2014
RERA registeredOct 2017
Proposed completionJun 2018
TodayJul 2026
02

Builder’s track record

RAJ-RERA · Promoter registration

BAGHERWAL INFRAPROJECTS LTD

OrganisationPromoter type
Kota, RajasthanBased in
1Projects
1City
2017–2018Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
2A RAJEEV GANDHI NAGAR, RAJEEV GANDHI NAGAR, JHALAWAR ROAD, KOTA, Ladpura, Kota, 324005
Taluka
Ladpura
District
Kota
Pincode
324005
What’s nearby
SchoolsNearest school 1.4km away · 6 educational institutions within 1km · College or university 247m away
HealthcareHospital 528m away · 4 clinics within 1km · Doctor's clinic within 1km
LifestylePark 1.6km away · 11+ restaurants and cafes within 1km
ShoppingSupermarket 100m away · Mall 405m away · Bank 918m away
Getting around
Expressway 4.2 km · Kota BypassPrimary road 253 mRailway line 1.3 km · Mumbai - Delhi RailwayRailway station 1.4km away (Dakaniya Talav)Limited bus connectivity nearby
Water & environment
Water body 434 m · CITY PARK DUCK POND
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹200.00 Cr declared. What that works out to:

35%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan
Building Permitapproved 3 Oct 2017 · 8 yrs ago

The promised possession date (30 Jun 2018) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.