Complete project overview

UP-RERA · Registration filing
Units
28 units
Unit mix
20 × 3 BHK · 8 × 2 BHK
Carpet area
53–90 sq mper unit, as filed
Floors
7
Land area
1,170 sq m

Timeline

Project startedMar 2020
RERA registeredApr 2020
Proposed completionNov 2024
TodayJul 2026

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

28 units across 28 batches
BuildingFloorTypeArea sq mCount
F13 BHK901
F13 BHK901
F13 BHK891
F13 BHK891
F23 BHK901
F23 BHK901
F23 BHK891
F23 BHK891
F33 BHK901
F33 BHK901
F33 BHK891
F33 BHK891
F43 BHK901
F43 BHK901
F43 BHK891
F43 BHK891
F53 BHK901
F53 BHK901
F53 BHK891
F53 BHK891
F62 BHK591
F62 BHK581
F62 BHK571
F62 BHK531
F72 BHK591
F72 BHK581
F72 BHK571
F72 BHK541

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

UP-RERA · Promoter registration

ROMA BUILDERS & PROMOTERS PVT. LTD.

CompanyPromoter type
4Registered projects
2Projects
1City
2017–2024Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
296 homeson the public record across 2 projects
1,170 sq mland declared
₹44.40 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

UP-RERA · Registration filing
District
Varanasi
Tehsil
Varanasi
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.2km away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 1.1 km · Mirzapur - Varanasi RoadPrimary road 799 m · National Highway 7Railway line 3.5 kmRailway station 4.7km away (Vyasnagar)Limited bus connectivity nearby
Water & environment
Water body 364 m
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹9.40 Cr declared to build 28 flats. What that works out to:

₹33.57 Lakhdeclared cost per flatall-in — land + construction

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

UP-RERA · Approved building plan
approved 30 Nov 2019 · 6 yrs ago
Building Permit no. 34/13 Gru. Ha. / Shaman / Vinyas / Vi. Pra. / 2019-20

The promised possession date (30 Nov 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

Completion Certificate — the occupancy sign-off, on record

A Completion Certificateis on this project’s RERA record (dated 26 Apr 2023)— the completion / legal-to-occupy sign-off that most RERA records simply don’t carry. It is issued by the planning authority, not by RERA. Still confirm it covers your specific unit before you rely on it.

Verify it yourself — look up plan 34/13 Gru. Ha. / Shaman / Vinyas / Vi. Pra. / 2019-20 on the approving authority’s portal to confirm the sanction.

Complaints register

None on record with UP-RERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — UP-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.