Complete project overview

RERA Telangana · Registration filing
Units
10 units
Unit mix
10 × 3BHK
Saleable area
205–206 sq mper unit, as filed
Floors
5
Land area
601 sq m
Built-up area
1,514 sq m

Timeline

RERA approvedAug 2022
Proposed completionAug 2025
TodayJul 2026
Construction progress

74% overall, as filed

Basement & plinth0%
Podiums0%
Superstructure90%
Internal finishes90%
Flat fit-out90%
Stairs & lifts90%
External finishes90%
OC-readiness90%
Excavation100%
Stilt floor100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

8 of 10 available
BuildingFloorTypeArea sq mAvailable
UMA RESIDENCY13BHK2051 of 1
UMA RESIDENCY13BHK2061 of 1
UMA RESIDENCY23BHKmortgaged2051 of 1
UMA RESIDENCY23BHKmortgaged2061 of 1
UMA RESIDENCY33BHK2051 of 1
UMA RESIDENCY33BHK2061 of 1
UMA RESIDENCY43BHK2050 of 1
UMA RESIDENCY43BHK2060 of 1
UMA RESIDENCY53BHK2051 of 1
UMA RESIDENCY53BHK2061 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

DANDE UMADEVI AND OTHERS

OthersPromoter type
Hyderabad, TelanganaBased in
1Projects
1City
2022–2025Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
PUNJAGUTTA HYDERABAD
Mandal
KHAIRTABAD
District
Hyderabad
Pincode
500082
North boundary
PLOT NO 2 H NO 6-3-347BY8
East boundary
LAND BELONGING TO NIZAM INSTITUTE OF M SCIENCES
South boundary
JB APURUPA ONE PARTMENT COMPLEX
West boundary
PART ROAD AND PLOT NO 1 H NO 6-3-347BY7
What’s nearby
Schools3 schools within 1km · 4 educational institutions within 1km · College or university 1.1km away
HealthcareHospital 76m away · 7 clinics within 1km · Pharmacy within 500m
LifestylePark 952m away · Gym or sports centre 688m away · 49+ restaurants and cafes within 1km
ShoppingSupermarket 253m away · Mall 1.0km away · Convenience store within 1km
Getting around
Expressway 253 m · Nagarjuna Circle RoadPrimary road 106 m · Nagarjuna Circle RoadRailway line 1.2 kmMetro station 393m away (Panjagutta)4 bus stops within 500m
Water & environment
Water body 329 m · jalagam vengal rao lake
distances only — not a flood assessment
Declared external development
Water supply90%
Sewerage (Chamber,…90%
Green Strip/TOT LO…90%
Rainwater90%
Electricity90%
Roads0%
Rainwater0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Renewable energy0%
Fire safety0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit

The promised possession date (27 Aug 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.