HORIZONMarkets
01

Complete project overview

RAJ-RERA · Registration filing
Land area
553 sq m
Completion deadline extended
2 extensions on record — latest to 15 Jun 2021declared reason: other than force majeure
Description
The copy of sanctioned layout plan received from Nagar Parishad Gangapur City wherein site plan is depicted is the only copy of site plan we have received from concerned authority apart from that no other site plan has been received.

Timeline

Construction startJun 2014
RERA registeredMar 2019
Proposed completionJun 2019
TodayJul 2026
02

Builder’s track record

RAJ-RERA · Promoter registration

Unity Infrateck

OrganisationPromoter type
Sawai Madhopur, RajasthanBased in
1Projects
1City
2019–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
Ward No. 23, Station Road, Gangapur, Sawai Madhopur, 322201
Taluka
Gangapur
District
Sawai Madhopur
Pincode
322201
What’s nearby
Schools5 schools within 1km · 6 educational institutions within 1km · Library 912m away
HealthcareHospital 185m away · 3 clinics within 1km · Doctor's clinic within 1km
Lifestyle2 parks within 500m · Gym or sports centre 269m away · 8 restaurants and cafes within 1km
ShoppingSupermarket 1.4km away · Mall 439m away · Convenience store within 1km
Getting around
Expressway 2.0 km · GangaPur Bypass RoadPrimary road 501 mRailway line 486 m · Mumbai - Delhi RailwayRailway station 511m away (Gangapur City)Bus stop within 1km
Water & environment
Water body 3.0 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹6.92 Cr declared. What that works out to:

55%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan

Urban Improvement Trust

Urban Improvement Trust
Building Permitapproved 14 Mar 2019 · 7 yrs ago

The promised possession date (15 Jun 2019) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Urban Improvement Trust

A city-level Urban Improvement Trust — Rajasthan's town-development body in cities without a development authority. It has approved 612 RERA projects across 20 districts about 1 in 4 in Rajasthan.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.