Complete project overview

RAJ-RERA · Registration filing
Land area
1,040 sq m

Timeline

Construction startMar 2021
RERA registeredMar 2021
Proposed completionMar 2028
TodayJul 2026
02

Builder’s track record

RAJ-RERA · Promoter registration

Bhiwadi Integrated Development Authority

OrganisationPromoter type
Alwar, RajasthanBased in
7Projects
1City
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
7 projectson the public record across 7 projects
17,429 sq mbuilt-up filed
1,46,770 sq mplotted area
1,98,830 sq mland declared
₹150.35 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
Khasra no. 322, Sector no. 6, Near UIT Guest House, BHIWADI, Alwar, Alwar, 301019
Village
BHIWADI
Taluka
Alwar
District
Alwar
Pincode
301019
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 38m away · 2 clinics within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 1.3 kmPrimary road 1.4 kmRailway line 3.3 km · Western Dedicated Freight CorridorNo metro or railway within 5kmLimited bus connectivity nearby
Price analysisdeclared build cost — not a sale price

₹64.37 Lakh declared. What that works out to:

₹575/sq ftof plotted area₹6,190/sq m

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan

Bhiwadi Integrated Development Authority

Development Authority
Layout Permitapproved 18 Mar 2021 · 5 yrs ago
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Bhiwadi Integrated Development Authority

Development authority

Has approved 59 RERA projects2.7% of Rajasthan.

an apartments market76% apartments · 24% plotted layouts. Layouts like yours are the smaller share here — this body mostly approves apartments.

Builders
39
On record
8,825 flats · 1,721 plots
Since
2017

More apartment-heavy than Rajasthan overall — 76% apartments here vs 34% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.