Complete project overview

RERA Telangana · Registration filing
Units
29 units
Unit mix
29 × Commercial Space
Saleable area
1309–1539 sq mper unit, as filed
Floors
5
Land area
2,702 sq m
Built-up area
6,272 sq m
Road widening
906 sq mland set aside for road widening

Timeline

RERA approvedJan 2020
Proposed completionJan 2026
TodayJul 2026
Construction progress

90% overall, as filed

Podiums0%
Excavation100%
Basement & plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

29 of 29 available
BuildingFloorTypeArea sq mAvailable
VAISHNAVI LAMANI ARCADE1Commercial Space1,3741 of 1
VAISHNAVI LAMANI ARCADE2Commercial Space1,5391 of 1
VAISHNAVI LAMANI ARCADE3Commercial Spacemortgaged1,3099 of 9
VAISHNAVI LAMANI ARCADE4Commercial Space1,3099 of 9
VAISHNAVI LAMANI ARCADE5Commercial Space1,3099 of 9

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

VAISHNAVI INFRA DEVELOPERS

PartnershipPromoter type
Hyderabad, TelanganaBased in
2Projects
2Cities
2020–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
29 homeson the public record across 2 projects
16,128 sq mbuilt-up filed
9,702 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Hyderabad Metropolitan Development Authority (HMDA)Urban Development Authoritythis project1 of 2 projects
Kalyan Dombivli Municipal CorporationMunicipal Corporation1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
KOMPALLE
Village
Kompally-Tanda
Mandal
Dundigal Gandimaisamma
District
Medchal-Malkajgiri
Pincode
500014
North boundary
NEIGHBOURS LAND
East boundary
LAND BELONGS TO P RADHIKA REDDY
South boundary
ROAD
West boundary
ROAD
What’s nearby
SchoolsNearest school 1.1km away · College or university 501m away
HealthcareHospital 471m away · 2 clinics within 1km
LifestyleNo parks within 2km · Swimming pool within 2km
ShoppingSupermarket 1.5km away · Bank 751m away
Getting around
Expressway 1.3 kmPrimary road 4.4 km · Jeedimetla Main RoadRailway line 2.1 kmRailway station 3.0km away (Gundla Pochampally)Limited bus connectivity nearby
Water & environment
Water body 997 m
distances only — not a flood assessment
Declared external development
Water supply100%
Sewerage (Chamber,…100%
Green Strip/TOT LO…100%
Street lighting100%
Rainwater100%
Renewable energy100%
Fire safety100%
Electricity100%
Roads0%
Rainwater0%
Community Building…0%
Sewage0%
Solid waste0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Hyderabad Metropolitan Development Authority (HMDA)

Urban Development Authority
Building Permit
Survey no. 158 & 160 PART

The promised possession date (23 Jan 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

HMDA

Urban Development Authority · Hyderabad metropolitan periphery

Has approved 3,643 RERA projectsabout 1 in 3 in Telangana.

an apartments market72% apartments · 28% plotted layouts. Apartments like yours are this body's core business.

Builders
2,462
On record
3,98,695 flats · 1,96,015 plots
Reach
71 mandals
Since
2016

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.