Complete project overview

RERA Telangana · Registration filing
Units
365 units
Unit mix
365 × 3BHK
Saleable area
159–245 sq mper unit, as filed
Floors
17
Buildings
3
Land area
16,188 sq m
Built-up area
68,300 sq m
Road widening
268 sq mland set aside for road widening

Timeline

RERA approvedAug 2022
Proposed completionAug 2028
TodayJul 2026
Construction progress

32% overall, as filed

Basement & plinth0%
Podiums0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal finishes40%
Superstructure80%
Excavation100%
Stilt floor100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

281 of 365 available
BuildingFloorTypeArea sq mAvailable
TOWER - A13BHKmortgaged1591 of 1
TOWER - A13BHKmortgaged1771 of 1
TOWER - A13BHKmortgaged2003 of 3
TOWER - A13BHKmortgaged2042 of 2
TOWER - A23BHKmortgaged1591 of 1
TOWER - A23BHKmortgaged1771 of 1
TOWER - A23BHKmortgaged2003 of 3
TOWER - A23BHKmortgaged2042 of 2
TOWER - A33BHKmortgaged1951 of 1
TOWER - A33BHKmortgaged1871 of 1
TOWER - A33BHKmortgaged2051 of 1
TOWER - A33BHKmortgaged2451 of 1
TOWER - A33BHKmortgaged2371 of 1
TOWER - A33BHKmortgaged2302 of 2
TOWER - A33BHKmortgaged2351 of 1
TOWER - A43BHKmortgaged1951 of 1
TOWER - A43BHK2051 of 1
TOWER - A43BHK2451 of 1
TOWER - A43BHK2371 of 1
TOWER - A43BHK2302 of 2
TOWER - A43BHKmortgaged2351 of 1
TOWER - A43BHK1870 of 1
TOWER - A53BHK1951 of 1
TOWER - A53BHK2051 of 1
TOWER - A53BHK2451 of 1
TOWER - A53BHK2371 of 1
TOWER - A53BHK2302 of 2
TOWER - A53BHK2351 of 1
TOWER - A53BHK1870 of 1
TOWER - A63BHK1871 of 1
TOWER - A63BHK2451 of 1
TOWER - A63BHK2371 of 1
TOWER - A63BHK2302 of 2
TOWER - A63BHK2351 of 1
TOWER - A63BHK1950 of 1
TOWER - A63BHK2050 of 1
TOWER - A73BHK1951 of 1
TOWER - A73BHK2051 of 1
TOWER - A73BHK2451 of 1
TOWER - A73BHK2371 of 1
TOWER - A73BHK2302 of 2
TOWER - A73BHK2351 of 1
TOWER - A73BHK1870 of 1
TOWER - A83BHK1951 of 1
TOWER - A83BHK1871 of 1
TOWER - A83BHK2051 of 1
TOWER - A83BHK2451 of 1
TOWER - A83BHK2371 of 1
TOWER - A83BHK2302 of 2
TOWER - A83BHK2351 of 1
TOWER - A93BHK2051 of 1
TOWER - A93BHK2451 of 1
TOWER - A93BHK2371 of 1
TOWER - A93BHK2302 of 2
TOWER - A93BHK1950 of 1
TOWER - A93BHK1870 of 1
TOWER - A93BHK2350 of 1
TOWER - A103BHK2051 of 1
TOWER - A103BHK2451 of 1
TOWER - A103BHK2302 of 2
TOWER - A103BHK1950 of 1
TOWER - A103BHK1870 of 1
TOWER - A103BHK2350 of 1
TOWER - A103BHK2370 of 1
TOWER - A113BHK2451 of 1
TOWER - A113BHK2371 of 1
TOWER - A113BHK2302 of 2
TOWER - A113BHK2351 of 1
TOWER - A113BHK1950 of 1
TOWER - A113BHK1870 of 1
TOWER - A113BHK2050 of 1
TOWER - A123BHK2051 of 1
TOWER - A123BHK2451 of 1
TOWER - A123BHK2371 of 1
TOWER - A123BHK2302 of 2
TOWER - A123BHK1950 of 1
TOWER - A123BHK1870 of 1
TOWER - A123BHK2350 of 1
TOWER - A133BHK2051 of 1
TOWER - A133BHK2451 of 1
TOWER - A133BHK2371 of 1
TOWER - A133BHK2302 of 2
TOWER - A133BHK1950 of 1
TOWER - A133BHK1870 of 1
TOWER - A133BHK2350 of 1
TOWER - A143BHK2051 of 1
TOWER - A143BHK2371 of 1
TOWER - A143BHK2302 of 2
TOWER - A143BHK1950 of 1
TOWER - A143BHK1870 of 1
TOWER - A143BHK2450 of 1
TOWER - A143BHK2350 of 1
TOWER - A153BHK1951 of 1
TOWER - A153BHK1871 of 1
TOWER - A153BHK2051 of 1
TOWER - A153BHK2451 of 1
TOWER - A153BHK2352 of 2
TOWER - A153BHK2302 of 2
TOWER - A163BHK2051 of 1
TOWER - A163BHK2451 of 1
TOWER - A163BHK2302 of 2
TOWER - A163BHK1951 of 1
TOWER - A163BHK1871 of 1
TOWER - A163BHK2351 of 1
TOWER - A163BHK2371 of 1
TOWER - A173BHK2051 of 1
TOWER - A173BHK2451 of 1
TOWER - A173BHK2302 of 2
TOWER - A173BHK1951 of 1
TOWER - A173BHK1871 of 1
TOWER - A173BHK2351 of 1
TOWER - A173BHK2371 of 1
TOWER - B13BHKmortgaged1771 of 1
TOWER - B13BHKmortgaged2004 of 4
TOWER - B13BHKmortgaged2042 of 2
TOWER - B23BHKmortgaged1771 of 1
TOWER - B23BHKmortgaged2004 of 4
TOWER - B23BHKmortgaged2042 of 2
TOWER - B33BHKmortgaged2451 of 1
TOWER - B33BHKmortgaged2371 of 1
TOWER - B33BHKmortgaged2302 of 2
TOWER - B33BHKmortgaged2351 of 1
TOWER - B33BHKmortgaged2311 of 1
TOWER - B33BHK2052 of 2
TOWER - B43BHK2451 of 1
TOWER - B43BHK2311 of 1
TOWER - B43BHK2052 of 2
TOWER - B43BHK2371 of 1
TOWER - B43BHK2302 of 2
TOWER - B43BHK2351 of 1
TOWER - B53BHK2451 of 1
TOWER - B53BHK2311 of 1
TOWER - B53BHK2052 of 2
TOWER - B53BHK2371 of 1
TOWER - B53BHK2302 of 2
TOWER - B53BHK2351 of 1
TOWER - B63BHK2311 of 1
TOWER - B63BHK2052 of 2
TOWER - B63BHK2371 of 1
TOWER - B63BHK2351 of 1
TOWER - B63BHK2450 of 1
TOWER - B63BHK2301 of 2
TOWER - B73BHK2451 of 1
TOWER - B73BHK2311 of 1
TOWER - B73BHK2052 of 2
TOWER - B73BHK2371 of 1
TOWER - B73BHK2351 of 1
TOWER - B73BHK2300 of 2
TOWER - B83BHK2311 of 1
TOWER - B83BHK2052 of 2
TOWER - B83BHK2371 of 1
TOWER - B83BHK2302 of 2
TOWER - B83BHK2351 of 1
TOWER - B83BHK2450 of 1
TOWER - B93BHK2311 of 1
TOWER - B93BHK2052 of 2
TOWER - B93BHK2371 of 1
TOWER - B93BHK2302 of 2
TOWER - B93BHK2351 of 1
TOWER - B93BHK2450 of 1
TOWER - B103BHK2451 of 1
TOWER - B103BHK2311 of 1
TOWER - B103BHK2052 of 2
TOWER - B103BHK2371 of 1
TOWER - B103BHK2351 of 1
TOWER - B103BHK2300 of 2
TOWER - B113BHK2451 of 1
TOWER - B113BHK2311 of 1
TOWER - B113BHK2371 of 1
TOWER - B113BHK2302 of 2
TOWER - B113BHK2351 of 1
TOWER - B113BHK2050 of 2
TOWER - B123BHK2371 of 1
TOWER - B123BHK2351 of 1
TOWER - B123BHK2052 of 2
TOWER - B123BHK2310 of 1
TOWER - B123BHK2300 of 2
TOWER - B123BHK2450 of 1
TOWER - B133BHK2451 of 1
TOWER - B133BHK2371 of 1
TOWER - B133BHK2311 of 1
TOWER - B133BHK2351 of 1
TOWER - B133BHK2051 of 2
TOWER - B133BHK2300 of 2
TOWER - B143BHK2451 of 1
TOWER - B143BHK2052 of 2
TOWER - B143BHK2371 of 1
TOWER - B143BHK2311 of 1
TOWER - B143BHK2351 of 1
TOWER - B143BHK2300 of 2
TOWER - B153BHK2451 of 1
TOWER - B153BHK2052 of 2
TOWER - B153BHK2371 of 1
TOWER - B153BHK2302 of 2
TOWER - B153BHK2311 of 1
TOWER - B153BHK2351 of 1
TOWER - B163BHK2451 of 1
TOWER - B163BHK2052 of 2
TOWER - B163BHK2371 of 1
TOWER - B163BHK2302 of 2
TOWER - B163BHK2311 of 1
TOWER - B163BHK2351 of 1
TOWER - B173BHK2451 of 1
TOWER - B173BHK2052 of 2
TOWER - B173BHK2371 of 1
TOWER - B173BHK2302 of 2
TOWER - B173BHK2311 of 1
TOWER - B173BHK2351 of 1
TOWER - C13BHKmortgaged1641 of 1
TOWER - C13BHKmortgaged1862 of 2
TOWER - C13BHKmortgaged1852 of 2
TOWER - C23BHKmortgaged1852 of 2
TOWER - C23BHKmortgaged1641 of 1
TOWER - C23BHKmortgaged1862 of 2
TOWER - C33BHKmortgaged2191 of 1
TOWER - C33BHKmortgaged1901 of 1
TOWER - C33BHKmortgaged2222 of 2
TOWER - C33BHKmortgaged2231 of 1
TOWER - C33BHKmortgaged1851 of 1
TOWER - C43BHKmortgaged2191 of 1
TOWER - C43BHK1901 of 1
TOWER - C43BHK2222 of 2
TOWER - C43BHK2230 of 1
TOWER - C43BHKmortgaged1850 of 1
TOWER - C53BHK2191 of 1
TOWER - C53BHK1901 of 1
TOWER - C53BHK2231 of 1
TOWER - C53BHK1851 of 1
TOWER - C53BHK2220 of 2
TOWER - C63BHK2222 of 2
TOWER - C63BHK2231 of 1
TOWER - C63BHK1900 of 1
TOWER - C63BHK1850 of 1
TOWER - C63BHK2190 of 1
TOWER - C73BHK2191 of 1
TOWER - C73BHK1851 of 1
TOWER - C73BHK2230 of 1
TOWER - C73BHK2221 of 2
TOWER - C73BHK1900 of 1
TOWER - C83BHK1851 of 1
TOWER - C83BHK2190 of 1
TOWER - C83BHK1900 of 1
TOWER - C83BHK2230 of 1
TOWER - C83BHK2220 of 2
TOWER - C93BHK1851 of 1
TOWER - C93BHK2190 of 1
TOWER - C93BHK1900 of 1
TOWER - C93BHK2221 of 2
TOWER - C93BHK2230 of 1
TOWER - C103BHK2222 of 2
TOWER - C103BHK1851 of 1
TOWER - C113BHK1900 of 2
TOWER - C113BHK2230 of 2
TOWER - C113BHK2191 of 2
TOWER - C123BHK2220 of 3
TOWER - C123BHK2232 of 3
TOWER - C133BHK2220 of 2
TOWER - C133BHK2230 of 2
TOWER - C133BHK1851 of 2
TOWER - C143BHK2230 of 1
TOWER - C143BHK1850 of 1
TOWER - C143BHK2221 of 2
TOWER - C143BHK1902 of 2
TOWER - C153BHK2231 of 1
TOWER - C153BHK1851 of 1
TOWER - C153BHK2220 of 2
TOWER - C153BHK2190 of 1
TOWER - C153BHK1900 of 1
TOWER - C163BHK2231 of 1
TOWER - C163BHK1851 of 1
TOWER - C163BHK2222 of 2
TOWER - C163BHK2191 of 1
TOWER - C163BHK1901 of 1
TOWER - C173BHK2231 of 1
TOWER - C173BHK1851 of 1
TOWER - C173BHK2222 of 2
TOWER - C173BHK2191 of 1
TOWER - C173BHK1901 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

VAJRAM CONSTRUCTIONS PVT LTD

CompanyPromoter type
Hyderabad, TelanganaBased in
3Projects
1City
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
466 homeson the public record across 3 projects
1,06,906 sq mbuilt-up filed
50,921 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
gopanapally
Village
Gopanpally
Mandal
Serilingampally
District
Ranga Reddy
Pincode
500046
North boundary
Sy No - 23-27
East boundary
Sy No - 34
South boundary
Main Road
West boundary
land belongs to jana rama rao
What’s nearby
SchoolsNearest school 1.1km away · College or university 1.1km away · Library 1.6km away
HealthcareHospital 1.3km away
LifestyleNo parks within 2km · Gym or sports centre 1.7km away
ShoppingSupermarket 1.6km away
Getting around
Expressway 4.1 km · Chandanagar - RC Puram BHEL Rd Mumbai HighwayPrimary road 2.3 km · Nallagandla FlyoverRailway line 2.4 kmRailway station 2.8km away (Lingampalli)Limited bus connectivity nearby
Water & environment
Water body 1.0 km
distances only — not a flood assessment
Government land classification

No residential (House Sites) class on record. The state classes this village’s land as Dry land. If it’s sold as residential plots, verify the layout’s conversion / approval.

Telangana Registration & Stamps
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit no. 2565/GHMC/SLP/2022-BPSurvey no. 28,29,30
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 2565/GHMC/SLP/2022-BP on the approving authority’s portal to confirm the sanction.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.