Complete project overview

RAJ-RERA · Registration filing
Land area
16,100 sq m
Completion deadline extended
1 extension on record — latest to 30 Jul 2021declared reason: force majeure
Description
As per the U.I.T., Kota layout plan approval letter no. F-7/D.T.P./2019/35 dated 31/01/2019 point no. 11, and remark put on the copy of approved layout plan “For Internal development in the scheme, 12.5 Percent saleable plot numbers A-44,A-45,A-46,A-47,A-48,A-49,A-69,A-80,A-81,A-82,A-83,A-84,A-85,A-86 Area admeasuring 1169.87 sq.mtr. are mortgage to U.I.T., Kota. These Plots will be demortgaged after the internal development.

Timeline

Construction startJan 2019
RERA registeredApr 2019
Proposed completionJul 2020
TodayJul 2026
02

Builder’s track record

RAJ-RERA · Promoter registration

VARDHAMAN ASSOCIATES

OrganisationPromoter type
Kota, RajasthanBased in
7Projects
5Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
196 homes · 93 plotson the public record across 7 projects
45,885 sq mbuilt-up filed
29,000 sq mplotted area
76,600 sq mland declared
₹18.73 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Urban Improvement TrustUrban Improvement Trustthis project2 of 3 projects
Pimpri Chinchwad Municipal CorporationMunicipal Corporation1 of 3 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
Khasra no. 367, 368, 906/378, Village Balita, Ladpura, Kota, 324008
Taluka
Ladpura
District
Kota
Pincode
324008
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 2.5km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 1.5 km · patan RoadRailway line 1.2 kmRailway station 2.6km away (Tirath)Limited bus connectivity nearby
Water & environment
Canal 1.6 kmRiver 1.6 km · Chambal RiverWater body 2.3 km · Chambal River
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹6.28 Cr declared. What that works out to:

₹362/sq ftof plotted area₹3,899/sq m
81%of the cost is land₹294/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan

Urban Improvement Trust

Urban Improvement Trust
Layout Permitapproved 16 Apr 2019 · 7 yrs ago

The promised possession date (30 Jul 2020) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Urban Improvement Trust

A city-level Urban Improvement Trust — Rajasthan's town-development body in cities without a development authority. It has approved 612 RERA projects across 20 districts about 1 in 4 in Rajasthan.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.