HORIZONMarkets
01

Complete project overview

RAJ-RERA · Registration filing
Land area
780 sq m
Completion deadline extended
2 extensions on record — latest to 2 Aug 2022declared reason: force majeure

Timeline

Construction startApr 2018
RERA registeredJun 2018
Proposed completionAug 2020
TodayJul 2026
02

Builder’s track record

RAJ-RERA · Promoter registration

VARDHMAN BUILDERS AND CONSTRUCTION

OrganisationPromoter type
Ajmer, RajasthanBased in
1Projects
1City
2018–2020Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
Plot no 8,9,10 situated at Khasra no 157, HARISH CHANDRA BHARGACA NAGAR, KIRANI PURA, Ajmer, Ajmer, 305001
Village
KIRANI PURA
Taluka
Ajmer
District
Ajmer
Pincode
305001
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 3.7km away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingSupermarket 1.5km away
Getting around
Expressway 251 m · Shreenagar RoadPrimary road 860 m · Shreenagar RoadRailway line 1.8 km · Western Dedicated Freight CorridorRailway station 1.9km away (Madar Junction)Limited bus connectivity nearby
Water & environment
Water body 4.3 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹6.35 Cr declared. What that works out to:

6%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan
Building Permitapproved 15 Jun 2018 · 8 yrs ago

The promised possession date (2 Aug 2020) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.