01

Complete project overview

RAJ-RERA · Registration filing
Land area
25,886 sq m
Completion deadline extended
1 extension on record — latest to 30 Apr 2018declared reason: other than force majeure
Description
Note:1. Due to lack of storage space in documents we have uploaded high quality scan of approved maps under tab of Building-Building sanction plan drawing no A-04, A-03, A-05, A-06, A-07, A-08, A-09, A-10, A-11, A-12, A-13, A-14, A-15, Building-Electrical drawing no A-02, Drawings Log Sheet and Building-Architectural drawings drawing no A-16, A-22, A-23, A-17, A-18, A-19, A-20, A-21, A-24, A-25, A-01a, A-01, A-01B. 2. Phase Area is 25985.71 sq mtrs not 25885.71 sq mtrs, additional fees and penalty for the extra 100 sq mtrs has been paid by way of IMPS No. - IMPS/P2A/734718433144/50200025185364HDFC dated 13/12/2017 Rs 5,000/-.As per remark the correct phase area has been rectified in Land Details of Registering Project.

Timeline

RERA registeredJan 2018
Proposed completionFeb 2018
TodayJul 2026
02

Builder’s track record

RAJ-RERA · Promoter registration

VEETRAG BUILDCON PRIVATE LIMITED

OrganisationPromoter type
Jodhpur, RajasthanBased in
1Projects
1City
2018–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
66/2, 66/10 and 628/65, Village Pal, Pal, Jodhpur, Jodhpur, 342014
Village
Pal
Taluka
Jodhpur
District
Jodhpur
Pincode
342014
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 3.3km away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 930 mPrimary road 4.0 kmRailway line 1.7 kmRailway station 3.1km away (Basni)Limited bus connectivity nearby
Water & environment
River 4.5 km · Jojari
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹149.67 Cr declared. What that works out to:

9%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan
Building Permitapproved 3 Jan 2018 · 8 yrs ago

The promised possession date (28 Feb 2018) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.