HORIZONMarkets
01

Complete project overview

RERA Andhra Pradesh · Registration filing
Units
30 flats
Unit mix
30 × 2BHK
Carpet area
67–77 sq m
Floors
5
Land area
1,397 sq m
Built-up area
3,577 sq m

Timeline

Project startedFeb 2022
RERA approvedJul 2023
Proposed completionDec 2024
TodayJul 2026

Find your flat

Every flat the builder registered, with the carpet area they filed. Look yours up and check it against what you were shown.

UnitTypeCarpet sq mBalcony sq mOuter wall sq mCommon sq mTotal sq mParking sq m
101GROUND FLOOR · VIHAN RESIDENCY2BHK68.733.235.3077.26
102GROUND FLOOR · VIHAN RESIDENCY2BHK77.186.134.4587.76
103GROUND FLOOR · VIHAN RESIDENCY2BHK69.613.233.6676.50
104GROUND FLOOR · VIHAN RESIDENCY2BHK75.622.06481.68
105GROUND FLOOR · VIHAN RESIDENCY2BHK71.283.235.3679.87
106GROUND FLOOR · VIHAN RESIDENCY2BHK66.722.975.3975.08
201FIRST FLOOR · VIHAN RESIDENCY2BHK68.733.235.3077.26
202FIRST FLOOR · VIHAN RESIDENCY2BHK77.186.134.4587.76
203FIRST FLOOR · VIHAN RESIDENCY2BHK69.613.233.6676.50
204FIRST FLOOR · VIHAN RESIDENCY2BHK75.622.06481.68
205FIRST FLOOR · VIHAN RESIDENCY2BHK71.283.235.3679.87
206FIRST FLOOR · VIHAN RESIDENCY2BHK66.722.975.3975.08
301SECOND FLOOR · VIHAN RESIDENCY2BHK68.733.235.3077.26
302SECOND FLOOR · VIHAN RESIDENCY2BHK77.186.134.4587.76
303SECOND FLOOR · VIHAN RESIDENCY2BHK69.613.233.6676.50
304SECOND FLOOR · VIHAN RESIDENCY2BHK75.622.06481.68
305SECOND FLOOR · VIHAN RESIDENCY2BHK71.283.235.3679.87
306SECOND FLOOR · VIHAN RESIDENCY2BHK66.722.975.3975.08
401THIRD FLOOR · VIHAN RESIDENCY2BHK68.733.235.3077.26
402THIRD FLOOR · VIHAN RESIDENCY2BHK77.186.134.4587.76
403THIRD FLOOR · VIHAN RESIDENCY2BHK69.613.233.6676.50
404THIRD FLOOR · VIHAN RESIDENCY2BHK75.622.06481.68
405THIRD FLOOR · VIHAN RESIDENCY2BHK71.283.235.3679.87
406THIRD FLOOR · VIHAN RESIDENCY2BHK66.722.975.3975.08
501FOURTH FLOOR · VIHAN RESIDENCY2BHK68.733.235.3077.26
502FOURTH FLOOR · VIHAN RESIDENCY2BHK77.186.134.4587.76
503FOURTH FLOOR · VIHAN RESIDENCY2BHK69.613.233.6676.50
504FOURTH FLOOR · VIHAN RESIDENCY2BHK75.622.06481.68
505FOURTH FLOOR · VIHAN RESIDENCY2BHK71.283.235.3679.87
506FOURTH FLOOR · VIHAN RESIDENCY2BHK66.722.975.3975.08

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. Carpet area is the legally meaningful number — not the super built-up figure a brochure quotes.

02

Builder’s track record

RERA Andhra Pradesh · Promoter registration

AKSHADHA INFRA

Partnership/LLP FirmPromoter type
SangareddyBased in
1Projects
1City
2023–2024Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Andhra Pradesh · Registration filing
Village
CHILAMATHUR
Mandal
Varadaiahpalem
District
Chittoor
Pincode
517541
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.9km away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 1.8 kmPrimary road 294 m · Tada - Sri Kalahasti RoadRailway line 2.0 kmRailway station 2.1km away (Tada)Limited bus connectivity nearby
Water & environment
Water body 434 mRiver 513 m
distances only — not a flood assessment
Government land classification

Land here includes House Sites (residential), plus Land abutting NH/SH/ZPP/MPP, Wet Land double crop, Agricultural Land fit for H.S.. The state classes land per survey— confirm your plot’s survey number is House Sites.

AP Registration & Stamps
Declared external development
Roads0%
Water supply0%
Sewage0%
Electricity0%
Solid waste0%
Fire safety0%
Water0%
Emergency exits0%
Renewable energy0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
Price analysisdeclared build cost — not a sale price

₹6.05 Cr declared to build 30 flats. What that works out to:

₹20.16 Lakhdeclared cost per flatall-in — land + construction
₹1,571/sq ftof built-up area₹16,909/sq m
6%of the cost is land₹244/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

Government guidance value
₹4,500/sq ydHouse Sites

₹5,382/sq m · effective Feb 2025 · revised up from ₹3,600

The state’s minimum value for this village’s land, set for stamp duty — a floor, not a market price. Source: AP Registration & Stamps.

04

Planning authority

RERA Andhra Pradesh · Approved building plan

Director, Town and Country Planning

Town & Country Planning (DTCP) · NELLORE
approved 7 Dec 2021 · 4 yrs ago
Building Permit no. 1105/0028/B/VARADIAHPALEM/CLAMTRU/2021Survey no. 124/14,124/15,125/1B

The promised possession date (7 Dec 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 1105/0028/B/VARADIAHPALEM/CLAMTRU/2021 on the approving authority’s portal (dtcp.ap.gov.in) to confirm the sanction.

The approving body, at scale

Nellore

Urban Development Authority

Has approved 140 RERA projects2.1% of Andhra Pradesh.

a mixed market69% apartments · 31% plotted layouts.

Builders
105
On record
2,323 flats · 6,564 plots
Reach
19 mandals
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Andhra Pradesh does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Andhra Pradesh does not publish a complaints register. This read cannot speak to them either way.
  • Escrow — RERA Andhra Pradesh does not publish escrow declarations. Whether buyer money is ring-fenced cannot be read here.