HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
10 units
Unit mix
10 × 3BHK
Saleable area
142–145 sq mper unit, as filed
Floors
5
Land area
446 sq m
Built-up area
1,239 sq m

Timeline

RERA approvedOct 2021
Proposed completionOct 2027
TodayJul 2026
Construction progress

100% overall, as filed

Excavation100%
Basement & plinth100%
Podiums100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

0 of 10 available
BuildingFloorTypeArea sq mAvailable
VIJAYA LAXMI RESIDENCY13BHK1450 of 1
VIJAYA LAXMI RESIDENCY13BHK1420 of 1
VIJAYA LAXMI RESIDENCY23BHKmortgaged1450 of 1
VIJAYA LAXMI RESIDENCY23BHKmortgaged1420 of 1
VIJAYA LAXMI RESIDENCY33BHK1450 of 1
VIJAYA LAXMI RESIDENCY33BHK1420 of 1
VIJAYA LAXMI RESIDENCY43BHK1450 of 1
VIJAYA LAXMI RESIDENCY43BHK1420 of 1
VIJAYA LAXMI RESIDENCY53BHK1450 of 1
VIJAYA LAXMI RESIDENCY53BHK1420 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

AKSHAYA ASSOCIATES

ProprietorshipPromoter type
Ranga Reddy, TelanganaBased in
3Projects
2Cities
2020–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
30 homeson the public record across 3 projects
3,584 sq mbuilt-up filed
1,209 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Hyderabad Metropolitan Development Authority (HMDA)Urban Development Authoritythis project2 of 3 projects
Greater Hyderabad Municipal Corporation (GHMC)Municipal / Corporation1 of 3 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
AMEENAPUR VILLAGE MANDAL , SANGA REDDY DIST
District
Sangareddy
Pincode
502032
North boundary
PLOT NO 113
East boundary
PLOT NO 87 AND 88
South boundary
PLOT NO 116
West boundary
12 M ROAD
What’s nearby
Schools1 school within 1km
HealthcareNearest hospital 2.5km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 2.6 km · RC Puram BHEL - Beeramguda Rd Mumbai HighwayPrimary road 3.2 kmRailway line 4.1 kmRailway station 4.2km away (Chandanagar)Limited bus connectivity nearby
Water & environment
Water body 1.2 km · Ameenpur Lake
distances only — not a flood assessment
Declared external development
Water supply100%
Sewerage (Chamber,…100%
Green Strip/TOT LO…100%
Rainwater100%
Electricity100%
Roads0%
Rainwater0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Renewable energy0%
Fire safety0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Hyderabad Metropolitan Development Authority (HMDA)

Urban Development Authority
Building Permit
Survey no. SY NO 161 OF PRIDE PARK OF AMEENAPUR VILL
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

HMDA

Urban Development Authority · Hyderabad metropolitan periphery

Has approved 3,643 RERA projectsabout 1 in 3 in Telangana.

an apartments market72% apartments · 28% plotted layouts. Apartments like yours are this body's core business.

Builders
2,462
On record
3,98,695 flats · 1,96,015 plots
Reach
71 mandals
Since
2016

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.