HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
20 units
Unit mix
20 × 2BHK
Saleable area
84–87 sq mper unit, as filed
Floors
5
Land area
644 sq m
Built-up area
1,719 sq m

Timeline

RERA approvedMar 2018
Proposed completionSep 2022
TodayJul 2026
Construction progress

57% overall, as filed

External finishes0%
OC-readiness5%
Flat fit-out15%
Stairs & lifts20%
Internal finishes50%
Stilt floor80%
Excavation100%
Basement & plinth100%
Podiums100%
Superstructure100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

15 of 20 available
BuildingFloorTypeArea sq mAvailable
Viswas Saketh Enclave12BHK872 of 3
Viswas Saketh Enclave12BHK841 of 1
Viswas Saketh Enclave22BHK872 of 3
Viswas Saketh Enclave22BHK840 of 1
Viswas Saketh Enclave32BHK870 of 1
Viswas Saketh Enclave32BHKmortgaged841 of 1
Viswas Saketh Enclave32BHKmortgaged872 of 2
Viswas Saketh Enclave42BHK872 of 3
Viswas Saketh Enclave42BHK841 of 1
Viswas Saketh Enclave52BHK873 of 3
Viswas Saketh Enclave52BHK841 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

Viswa avenues private limited

CompanyPromoter type
Ranga Reddy, TelanganaBased in
2Projects
2Cities
2018–2026Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
65 homeson the public record across 2 projects
7,943 sq mbuilt-up filed
2,531 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
Near DAV Public School
Village
Old Hafeezpet
Mandal
Serilingampally
District
Ranga Reddy
Pincode
500049
North boundary
plot nos 877-878-879
East boundary
plot no 868
South boundary
40 feet wide road
West boundary
plot no 871
What’s nearby
Schools1 school within 500m · 6 educational institutions within 1km · Kindergarten within 500m
HealthcareHospital 447m away · Pharmacy within 1km
LifestylePark 719m away · Gym or sports centre 560m away · 10+ restaurants and cafes within 1km
ShoppingSupermarket 181m away · Mall 1.9km away · Convenience store within 1km
Getting around
Expressway 232 m · Nizampet - Miyapur Road Mumbai HighwayPrimary road 559 m · Bollaram RoadRailway line 1.4 kmMetro station 700m away (miyapur metro)2 bus stops within 500m
Water & environment
Water body 569 m
distances only — not a flood assessment
Declared external development
Water supply20%
Sewerage (Chamber,…10%
Roads0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit no. 2/c12/05004/2018Survey no. 54

The promised possession date (1 Sep 2022) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 2/c12/05004/2018 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.