Developer · builder dossier
RATAN HOUSING DEVELOPMENT LIMITED Uttar Pradesh · Maharashtra
gethorizon.in/builders/ratan-housing-development-limited RATAN HOUSING DEVELOPMENT LIMITED has 11 projects on the public RERA record across 2 states, first registered 2017 through 2022.
What they build
Residential 91% Other 9%
01
Portfolio, summed Everything the builder declared at registration, added up across the projects on the record.
11 Projects
3 Cities
2017–2024 On the record
2,033 flats declared
11,921 sq m built-up declared
₹496.00 Cr declared build cost Every figure is drawn from the official RERA government registers — as each project declared it, not an independent measurement.
What they build 11 projects Residential 10 91% Other 1 9% Where they build Uttar Pradesh 9 projects Maharashtra 2 projects Top cities Kanpur Nagar 6 projects Lucknow 3 projects Pune City 2 projects 02
Track record over time When their projects were registered, and when the filed pipeline is due to complete.
Timeline every project, start → promised completion
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 today
03
On the record legally What the public register carries about delivery and disputes — facts to raise in a meeting, never a verdict.
1 Marked complete
10 Still ongoing
10 Possession date passed 18 complaints on the record, across 5 projects. 1 project with a lapsed, revoked, surrendered or in-abeyance registration. 5 projects filed a revised (extended) completion date. Projects carrying a flag on the record Complaints, litigation and escrow are shown only where the state authority publishes them, and many do not. An absent signal is silence, not proof of a clean record — verify with the authority and your own lawyer.
04
The projects 11 on the record All 11 Residential 10 Other 1
Residential
Ratan Galaxy Phase II RATAN HOUSING DEVELOPMENT LIMITED · Lucknow
2 yr 8 mo
Mar 2022 registered
Nov 2024 target completion
Units 137 unitsCarpet area 11–170 sq mUnit mix 72 × 3 BHK · 36 × 2 BHK +2 more
Residential
Sai Ratan Prestige RATAN HOUSING DEVELOPMENT LIMITED · Bakshi Ka Talab** · Lucknow
2 yr 5 mo
Jan 2020 registered
Jun 2022 target completion
Units 64 unitsUnit mix 40 × 3 BHK · 24 × 2 BHKCarpet area 85–103 sq m
Residential / Group Housing
Ratan Neptune Phase 3 RATAN HOUSING DEVELOPMENT LIMITED · Pune (M Corp.) · Pune City
5 yr 3 mo
Sep 2019 registered
Dec 2024 target completion
Floors 9Buildings 2Land area 9,308 sq m
Residential
RATAN MAHESH RATAN HOUSING DEVELOPMENT LIMITED · Kanpur · Kanpur Nagar
3 yr 11 mo
Feb 2018 registered
Jan 2022 target completion
Units 54 unitsUnit mix 30 × 2 BHK · 24 × 3 BHKCarpet area 60–82 sq m
Residential
RATAN ANAND RATAN HOUSING DEVELOPMENT LIMITED · Kanpur · Kanpur Nagar
4 yr 7 mo
Feb 2018 registered
Sep 2022 target completion
Units 72 unitsUnit mix 57 × 2 BHK · 15 × 3 BHKCarpet area 54–104 sq m
Residential
RATAN GRAND PHASE 1 RATAN HOUSING DEVELOPMENT LIMITED · Bilhaur · Kanpur Nagar
4 yr 11 mo
Feb 2018 registered
Jan 2023 target completion
Units 371 unitsUnit mix 336 × 2 BHK · 34 × SHOP · 1 × OTHERCarpet area 15–998 sq m
Residential
RATAN ORBIT (PHASE -I) RATAN HOUSING DEVELOPMENT LIMITED · Kanpur · Kanpur Nagar
4 mo
Aug 2017 registered
Dec 2017 target completion
Units 912 unitsUnit mix 600 × 3 BHK · 312 × 2 BHKCarpet area 64–144 sq m
Residential
RATAN ORBIT (PHASE-II) RATAN HOUSING DEVELOPMENT LIMITED · Kanpur · Kanpur Nagar
2 yr 4 mo
Aug 2017 registered
Dec 2019 target completion
Units 144 unitsUnit mix 96 × 2 BHK · 48 × 3 BHKCarpet area 83–127 sq m
Residential
RATAN GALAXY (PHASE I) RATAN HOUSING DEVELOPMENT LIMITED · Lucknow
10 mo
Aug 2017 registered
Jun 2018 target completion
Units 252 unitsUnit mix 164 × 2 BHK · 72 × 3 BHK · 16 × 4 BHKCarpet area 69–170 sq m
Residential
RATAN JEWELS RATAN HOUSING DEVELOPMENT LIMITED · Kanpur · Kanpur Nagar
10 mo
Aug 2017 registered
Jun 2018 target completion
Units 27 unitsUnit mix 27 × 3 BHKCarpet area 106–111 sq m
Others
RATAN NEPTUNE PHASE 2 RATAN HOUSING DEVELOPMENT LIMITED · Pune (M Corp.) · Pune City
1 yr 5 mo
Jul 2017 registered
Dec 2018 target completion
Floors 18Parking 87 spacesLand area 2,784 sq m