Still due — nearest target completion first, using the revised date where one is filed.
Plotted Development
JD ASHWASURYA LAVISH
JD DEVELOPERS AND PROMOTERS · Nelamangala
1 yr 11 mo
Oct 2024started
Sep 2026target completion
Plots127 plotsLand parcels3 survey nos
Apartment
AISHWARYA GREEN HOMES
AISHWARYA DEVELOPERS · Bengaluru South
2 yr 1 mo
Aug 2024started
Sep 2026target completion
Units28 unitsUnit mix24 × 3 BHK · 4 × 2 BHKTowers1
Apartment
ALCHEMY ELIXIR
ARATT CITY TOWERS LLP · Anekal
4 yr
Sep 2022started
Sep 2026target completion
Units349 unitsUnit mix349 × FlatsTowers2
Apartment
Assetz Soho & Sky
APG Imperial Homes Private Limited · Yelahanka
4 yr 5 mo
Apr 2022started
Sep 2026target completion
Units114 unitsUnit mix114 × ApartmentsTowers5
Apartment
BHAVYA DAZZLE
Bhavya Builders · Anekal
4 yr 11 mo
Oct 2021started
Sep 2026target completion
Units168 unitsUnit mix144 × 2 BHK · 24 × 3 BHKTowers1
Apartment
Blisston
Gurusamy SelvaKumar · Bengaluru South
4 yr 8 mo
Jan 2022started
Sep 2026target completion
Units16 unitsUnit mix16 × Residential FlatsTowers1
Plotted Development
Concorde Abode 99
Concorde Millennium LLP · Bengaluru South
5 yr 5 mo
Apr 2021started
Sep 2026target completion
⚠ no escrow declaredPlots159 plotsLand area49,270 sq mCovered area21,770 sq m
Residential/Group Housing
Evershine NORTHEAST Apartments
Evershine Dwellings Pvt ltd · Anekal
4 yr 11 mo
Oct 2021started
Sep 2026target completion
⚠ no escrow declaredTowers2Land area6,930 sq mFAR sanctioned2.24
Apartment
FORTUNERS INFRA ELIXIR
FORTUNERS INFRA · Anekal
2 yr 5 mo
Apr 2024started
Sep 2026target completion
Units60 unitsUnit mix36 × 2BHK · 20 × 3BHK · 4 × 1BHKTowers1
Plotted Development
GEOWN OASIS PHASE - 2A
GEOWN CASPER PROPERTIES PRIVATE LIMITED · Anekal
10 mo
Nov 2025started
Sep 2026target completion
Plots19 plotsLand parcels2 survey nos
Apartment
Greenfinch Meadows
Greenfinch Projects Pvt Ltd · Bengaluru East
4 yr 2 mo
Jul 2022started
Sep 2026target completion
Units181 unitsTowers2Unit mix12 × AT2-2BHK · 12 × BT7-3BHK
Mixed Development
SBR EARTH & SKY
SBR INFRASPACE · Bengaluru East
4 yr 1 mo
Aug 2022started
Sep 2026target completion
Units135 unitsUnit mix135 × Villaments · 2 × Commercial SpaceTowers2
Apartment
SREE ADITHYA LOTUS PARK
SREE ADITHYA DEVELOPERS · Bengaluru East
2 yr 8 mo
Jan 2024started
Sep 2026target completion
Units141 unitsUnit mix93 × 2 BHK Flats · 48 × 3 BHK FlatsTowers2
Apartment
SRI RAMA ENCLAVE
MEGA INFRA · Yelahanka
2 yr 9 mo
Dec 2023started
Sep 2026target completion
Units64 unitsUnit mix52 × 3 BHK · 12 × 2 BHKTowers2
Apartment
SUVRITH SHELTER
SUVRITH STRUCTURES · Bengaluru South
2 yr 2 mo
Jul 2024started
Sep 2026target completion
Units124 unitsUnit mix80 × 3 BHK · 44 × 2 BHKTowers1
Apartment
The lake Terraces
KEYA HOMES INFRA LLP · Anekal
2 yr 7 mo
Feb 2024started
Sep 2026target completion
Units409 unitsUnit mix322 × 2 BHK · 46 × 3 BHK · 41 × 1 BHKTowers2
Row Houses
TRIFECTA VERDEEN RESPLANDOR ROW HOUSE PHASE-3
TRIFECTA PROJECTS PRIVATE LIMITED · Bengaluru East
2 yr 6 mo
Mar 2024started
Sep 2026target completion
Units49 unitsUnit mix49 × 4 BHKTowers2
Plotted Development
Under the Sun – Luxury Villa Lifestyle by Fortius
FORTIUS LAND DEVELOPERS LLP · Devanahalli
3 yr 11 mo
Oct 2022started
Sep 2026target completion
Plots39 plotsLand parcels1 survey no
Apartment
VBHC Haven of Joy
VBHC Mumbai Value Homes Pvt Ltd · Bengaluru South
4 yr 8 mo
Jan 2022started
Sep 2026target completion
Units440 unitsTowers4Unit mix160 × 2BR REG Type 1 RESIDENTIAL UNITS · 140 × 2BR REG Type 2 RESIDENTIAL UNITS
Residential/Group Housing
DNR HIGHLINE
DNR CORPORATION PRIVATE LIMITED · Bengaluru North
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredTowers2Land area12,262 sq mFAR sanctioned3.54
Apartment
ELV High Garden
ELV Projects Private Limited · Bengaluru East
4 yr
Oct 2022started
Oct 2026target completion
⚠ 1 open complaintUnits219 unitsUnit mix160 × 2BHK · 36 × 3BHK · 23 × 2.5BHKTowers1
Residential/Group Housing
Chitradurga City-292 DUS under PMAY(U)-HFA
KARNATAKA SLUM DEVELOPMENT BOARD · Chitradurga
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area13,096 sq mCovered area9,723 sq mOpen area3,372 sq m
Residential/Group Housing
Construction of 484 Ground Floor units in Variou
KSDB · Bengaluru South
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area21,708 sq mCovered area16,117 sq mOpen area5,735 sq m
Residential/Group Housing
construction 500 houses in padmanabanara
karnatak a slum development board · Bengaluru South
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area22,425 sq mCovered area16,650 sq mOpen area5,775 sq m
Residential/Group Housing
CONSTRUCTION OF 1000 HOUSES AT MAHADEVAPURA
KSDB · Bengaluru East
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area44,850 sq mCovered area33,300 sq mOpen area11,550 sq m
Residential/Group Housing
Construction of 1000 Houses in T Dasarahalli
Karnataka Slum Development Board · Bengaluru North
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area44,850 sq mCovered area33,300 sq mOpen area11,550 sq m
Residential/Group Housing
Construction of 1176 Houses at Dandeli town
KARNATAKA SLUM DEVELOPMENT BOARD · Haliyala
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area52,744 sq mCovered area39,161 sq mOpen area13,583 sq m
Residential/Group Housing
Construction of 1200 (GF) HOUSES at Bommanahalli
karnataka slum development board · Bengaluru South
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area53,820 sq mCovered area39,960 sq mOpen area13,860 sq m
Residential/Group Housing
Construction of 1200 houses in Tiptur City
Karnataka Slum Development Board · Tiptur
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area53,820 sq mCovered area39,960 sq mOpen area13,860 sq m
Residential/Group Housing
CONSTRUCTION OF 130 DU'S
KSDB · Anekal
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area5,830 sq mCovered area4,329 sq mOpen area1,501 sq m
Residential/Group Housing
Construction of 1430 Houses in CV Raman Nagar
KARNATAKA SLUM DEVELOPMENT BOARD · Bengaluru South
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area58,864 sq mCovered area43,520 sq mOpen area15,344 sq m
Residential/Group Housing
Construction of 200 houses in Nelamangla Town
KARNATAKA SLUM DEVELOPMENT BOARD · Nelamangala
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area8,970 sq mCovered area6,660 sq mOpen area2,310 sq m
Residential/Group Housing
Construction of 300 houses in gubbi Town
Karnataka Slum Development Board · Gubbi
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area13,455 sq mCovered area9,990 sq mOpen area3,465 sq m
Residential/Group Housing
Construction of 400 Du's in KGF City
KSDB · Bangarapet
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area17,940 sq mCovered area13,320 sq mOpen area4,620 sq m
Residential/Group Housing
Construction of 400Dus in Malur
KSDB · Maluru
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area17,940 sq mCovered area13,320 sq mOpen area4,620 sq m
Residential/Group Housing
Construction of 412 Housese in Hebbala
Karnataka Slum Development Board · Bengaluru North
4 yr 11 mo
Nov 2021started
Oct 2026target completion
⚠ no escrow declaredLand area18,478 sq mCovered area13,720 sq mOpen area4,759 sq m
Residential/Group Housing
Construction of 423 Houses in Vijayappura & Devan
Karnataka Slum Development Board · Devanahalli
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area18,972 sq mCovered area14,086 sq mOpen area4,886 sq m
Residential/Group Housing
Construction of 455 Houses at Kerur Town
KARNATAKA SLUM DEVELOPMENT BOARD · Badami
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area20,407 sq mCovered area15,152 sq mOpen area5,255 sq m
Residential/Group Housing
CONSTRUCTION OF 494 HOUSES
KSDB · Hosakote
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area22,156 sq mCovered area16,451 sq mOpen area5,706 sq m
Residential/Group Housing
CONSTRUCTION OF 500 HOUSES
KSDB · Bengaluru East
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area22,425 sq mCovered area16,650 sq mOpen area5,775 sq m
Residential/Group Housing
Construction of 520 houses in Koratagere Town
Karnataka Slum Development Board · Kortagere
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area23,322 sq mCovered area17,316 sq mOpen area6,006 sq m
Residential/Group Housing
Construction of 625 Houses @ HubliDharwad central
KARNATAKA SLUM DEVELOPMENT BOARD · Hubballi
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area28,031 sq mCovered area20,813 sq mOpen area7,219 sq m
Residential/Group Housing
Construction of 760 Dus in chikkaballapura Town
Karnataka Slum Development Board · Chikkaballapur
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area34,086 sq mCovered area25,308 sq mOpen area8,778 sq m
Residential/Group Housing
Davangere North - 828 DUS under PMAY(U)-HFA
KARNATAKA SLUM DEVELOPMENT BOARD · Davanagere
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area37,135 sq mCovered area27,572 sq mOpen area9,563 sq m
Residential/Group Housing
Construction of 1350 @ Hubli-Dharwad city
KARNATAKA SLUM DEVELOPMENT BOARD · Dharwad
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area60,548 sq mCovered area44,955 sq mOpen area15,593 sq m
Residential/Group Housing
Construction of 240 (G+3) at BETTADASANPURA
KARNATAKA SLUM DEVELOPMENT BOARD · Bengaluru South
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area10,522 sq mCovered area5,000 sq mOpen area5,522 sq m
Residential/Group Housing
Constrution of 500 Houses in Basvangudi
Karnataka Slum Development Board · Bengaluru South
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area22,425 sq mCovered area16,650 sq mOpen area5,775 sq m
Residential/Group Housing
Constuction Of 698 Du In In Kanakapura
Karnataka slum devolpment board Banglore · Kanakapura
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area93,078 sq mCovered area46,500 sq mOpen area46,578 sq m
Residential/Group Housing
construction 375 Dus at Navalgunda Town.
Karnataka slum development board · Navalagunda
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area16,819 sq mCovered area12,488 sq mOpen area4,331 sq m
Residential/Group Housing
Construction of 1035 @ Raybag
KARNATAKA SLUM DEVELOPMENT BOARD · Raibagh
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area46,419 sq mCovered area34,465 sq mOpen area11,954 sq m
Residential/Group Housing
Construction of 1748 @ Belagavi South
KARNATAKA SLUM DEVELOPMENT BOARD · Belagavi
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area78,397 sq mCovered area58,208 sq mOpen area20,189 sq m
Residential/Group Housing
Construction of 200 at Kitturu Town under PMAY(U)
KARNATAKA SLUM DEVELOPMENT BOARD · Belagavi
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area8,970 sq mCovered area6,660 sq mOpen area2,310 sq m
Residential/Group Housing
Construction of 200 Houses at karwar
KARNATAKA SLUM DEVELOPMENT BOARD · Ankola
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area8,970 sq mCovered area6,660 sq mOpen area2,310 sq m
Residential/Group Housing
Construction of 235 Houses at Kundagola Town
KARNATAKA SLUM DEVELOPMENT BOARD · Kundagola
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area10,540 sq mCovered area7,826 sq mOpen area2,714 sq m
Residential/Group Housing
Construction of 250 Houses at Indi town.
KARNATAKA SLUM DEVELOPMENT BOARD · Indi
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area11,212 sq mCovered area8,325 sq mOpen area2,887 sq m
Residential/Group Housing
Construction of 250 Houses at Kalaghatagi
KARNATAKA SLUM DEVELOPMENT BOARD · Kalaghati
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area11,213 sq mCovered area8,325 sq mOpen area2,888 sq m
Residential/Group Housing
Construction of 250 Houses at Sindagi town.
KARNATAKA SLUM DEVELOPMENT BOARD · Sindagi
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area11,212 sq mCovered area8,325 sq mOpen area2,887 sq m
Residential/Group Housing
Construction of 275 Houses at Badami Town
KARNATAKA SLUM DEVELOPMENT BOARD · Badami
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area12,334 sq mCovered area9,158 sq mOpen area3,176 sq m
Residential/Group Housing
Construction of 313 @ Bhtkala
KARNATAKA SLUM DEVELOPMENT BOARD · Uttara Kannada
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area14,038 sq mCovered area10,422 sq mOpen area3,615 sq m
Residential/Group Housing
Construction of 411 Houses at Kumta Town.
KARNATAKA SLUM DEVELOPMENT BOARD · Kumta
5 yr
Oct 2021started
Oct 2026target completion
⚠ no escrow declaredLand area18,433 sq mCovered area13,686 sq mOpen area4,748 sq m