Registration lapsed

This project’s MahaRERA registration has lapsed— it expired and was not renewed. A lapsed project may be stalled, finished-but-not-updated, or abandoned; the record stops here and RERA’s ongoing protections may no longer apply. Confirm the current status directly with MahaRERA before you rely on anything below.

01

Complete project overview

MahaRERA · Registration filing
Floors
12
Buildings
2
Parking
846 spaces
Land area
6,116 sq m
Sanctioned built-up
14,408 sq m

Timeline

RERA registeredOct 2022
Proposed completionMar 2025
TodayJul 2026
02

Builder’s track record

MahaRERA · Promoter registration

99 AVENUE REALTY LLP

PartnershipPromoter type
Pune, MAHARASHTRABased in
1Projects
1City
2022–2025Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Pune (M Corp.)
Taluka
Pune City
District
Pune
Pincode
411040
Survey no.
SNO595/2 CTS 3293B PLOT
North boundary
UNIT A3 BUILDING
East boundary
9 M ROAD
South boundary
RING ROAD
West boundary
9 M ROAD
What’s nearby
Schools2 schools within 1km · Library 1.7km away
HealthcareHospital 846m away · 4 clinics within 1km · Doctor's clinic within 1km
LifestylePark 635m away
ShoppingSupermarket 1.1km away
Getting around
Expressway 2.0 km · Jagannath Shankarsheth MargPrimary road 52 m · Chhatrapati Shivaji Maharaj FlyoverRailway line 3.5 km · Pune - Miraj Railway LineMetro station 3.5km away (Swargate)Limited bus connectivity nearby
04

Planning authority

MahaRERA · Approved building plan

Pune Municipal Corporation

Municipal Corporation
Building Permit
Survey no. SNO595/2 CTS 3293B PLOT

The promised possession date (31 Mar 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pune Municipal Corporation

Municipal corporation

Has approved 1,863 RERA projectsabout 1 in 11 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,351
On record
9,749 flats · 439 plots
Reach
3 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.