Complete project overview

MahaRERA · Registration filing
Floors
16
Buildings
2
Parking
47 spaces
Land area
1,740 sq m
Sanctioned built-up
7,857 sq m

Timeline

RERA registeredAug 2022
Proposed completionJun 2027
TodayJul 2026
Construction progress
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Water conservation…0%
Electrical meter r…0%
Flat fit-out30%
Internal finishes85%
External finishes85%
OC-readiness85%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Stilt floor100%
Superstructure100%
Stairs & lifts100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Kothari Housing Company

PartnershipPromoter type
Nashik, MAHARASHTRABased in
1Projects
1City
2022–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Nashik
Taluka
Nashik
District
Nashik
Pincode
422222
Survey no.
Plot No 2+3 S No 156/2/2A+ 156/2/2B
North boundary
By plot no 4
East boundary
By 30 Mtrs wide DP road
South boundary
By 15 Mtrswide road
West boundary
By plot no 5-6
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 703m away
LifestylePark 1.7km away
ShoppingNo supermarket within 2km
Getting around
Expressway 4.8 kmPrimary road 138 m · Gangapur RoadNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 552 mRiver 815 m · Godavari
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Nashik Municipal Corporation

Municipal Corporation
Building Permit
Survey no. Plot No 2+3 S No 156/2/2A+ 156/2/2B
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Nashik Municipal Corporation

Municipal corporation

Has approved 821 RERA projectsabout 1 in 24 in Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
692
On record
4,331 flats · 111 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.