HORIZON
Share

Aasma Enclave 15

P50500077859 · MahaRERA · https://gethorizon.in/projects/aasma-enclave-15-nagpur-m-corp-nagpur-urban-w3do02ej

01

Complete project overview

MahaRERA · Registration filing
Floors
6
Parking
36 spaces
Land area
855 sq m
Sanctioned built-up
2,068 sq m

Timeline

RERA registeredNov 2024
Proposed completionJun 2027
TodaySep 2026
Construction progress
Basement (if any)0%
Podiums0%
Water Supply0%
Landscaping & Tree…0%
Water conservation…0%
Fire protection an…0%
Excavation100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

Aasma Buildcon

PartnershipPromoter type
Nagpur, MAHARASHTRABased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Nagpur (M Corp.)
Taluka
Nagpur (Urban)
District
Nagpur
Pincode
440030
Survey no.
Plot No. 2D,1D, KH. No. 34/1, 34/10, 34/5, 34/9, Shri Swamy Samartha Vasahat, Dist-Nagpur.
North boundary
9 meter Road
East boundary
9 meter Road
South boundary
9 meter Road
West boundary
Plot Number 8
What’s nearby
SchoolsNearest school 1.4km away
HealthcareHospital 873m away · 1 clinic within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 1.4 kmPrimary road 1.4 kmRailway line 1.0 kmRailway station 1.3km away (Godhani)Limited bus connectivity nearby
Water & environment
River 1.1 km · Pivli NadiWater body 2.9 km · Gorewada lake
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra IGR — Annual Statement of Rates

In Maharashtra it’s called the ready reckoner rate.

₹33,571per sq yd
₹40,150per sq m
Which rate
residential flat (built)
Matched to
The middle rate across the 84 divisions of “Nagpur (M Corp.)” — the city's middle, not this project's own division.
In force
2026-2027 schedule
Spread
₹17,709₹86,288 per sq yd across the places it was taken over

What this number is — and isn’t

  • The minimum value Maharashtra’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
  • Not a market price. Sales normally register above it, and how far above varies by place and by project.
  • Its fit depends on the grain the state publishes at. This one is matched at the level of city, and says so above. How Horizon decides what to show.
05

Planning authority

MahaRERA · Approved building plan

Nagpur Improvement Trust

Building Permit
Survey no. Plot No. 2D,1D, KH. No. 34/1, 34/10, 34/5, 34/9, Shri Swamy Samartha Vasahat, Dist-Nagpur.
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Nagpur Improvement Trust

Planning authority

Has approved 109 RERA projects0.5% of Maharashtra.

an apartments market95% apartments · 5% plotted layouts. Apartments like yours are this body's core business.

Builders
93
On record
2,588 flats · 759 plots
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

435 residential projects still under way within 25 km. Step out ring by ring:

16 projects within 1 km — showing the nearest 6.

NagpurResidential / Group Housing

GOKUL ENCLAVE WING C WING D

HARE KRISHNA BUILDERS

Mar 2022registered
Dec 2027target completion
Government Guidance Rate₹33,571/sq ydAuthorityMahaRERA
THE MOUZA- ZINGABAI TAKALIResidential / Group Housing

ROYAL PRIDE

SHIBAAM INFRACON PRIVATE LIMITED

Feb 2026registered
Dec 2029target completion
Government Guidance Rate₹36,045/sq ydScale48 flatsAuthorityMahaRERA
NagpurResidential / Group Housing

GAJANAN ENCLAVE

SHREE GAJANAN BUILDERS AND DEVELOPERS

Jan 2022registered
Dec 2027target completion
Government Guidance Rate₹33,571/sq ydScale36 flatsAuthorityMahaRERA
NagpurResidential / Group Housing

ARFAH PARK AVENUE

HR CONSTRUCTION & ASSOCIATES

Jun 2025registered
Mar 2027target completion
Government Guidance Rate₹33,571/sq ydScale37 flatsAuthorityMahaRERA
NagpurMixed

GIRIRAJ RESIDENCY-II

GREENSTONE INFRASTRUCTURE

Oct 2024registered
Mar 2029target completion
Government Guidance Rate₹33,571/sq ydScale49 flatsAuthorityMahaRERA
NagpurResidential / Group Housing

SHIV GOVIND DAFFODIL

RB CONSTRUCTION

Oct 2024registered
Mar 2028target completion
Government Guidance Rate₹33,571/sq ydScale36 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.