01

Complete project overview

MahaRERA · Registration filing
Floors
6
Buildings
2
Land area
745 sq m
Sanctioned built-up
1,665 sq m

Timeline

RERA registeredMay 2022
Proposed completionDec 2026
TodaySep 2026
02

Builder’s track record

MahaRERA · Builder registration

Kayum Ali Parkar

IndividualPromoter type
Ratnagiri, MAHARASHTRABased in
4Projects
1City
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
51 homeson the public record across 4 projects
4,102 sq mbuilt-up filed
2,576 sq mland declared

These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from Kayum Ali Parkar— the full portfolio →

03

Location

MahaRERA · Registration filing
Village
Mauje Dapoli
Taluka
Dapoli
District
Ratnagiri
Pincode
415712
Survey no.
25/6/4, 25/6/6
North boundary
MASJID
East boundary
INTERNAL ROAD
South boundary
PLOT NO 92 AND 94
West boundary
INTERNAL ROAD
What’s nearby
Schools2 schools within 1km · 3 educational institutions within 1km · Library 597m away
HealthcareHospital 147m away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km · Bank 309m away
Getting around
Primary road 5 mNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
River 354 m
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Maharashtra's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Dapoli Nagarpanchayat Dapoli

Building Permit
Survey no. 25/6/4, 25/6/6
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that approved this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

07

Other projects nearby

The register · within 25 km

53 residential projects still under way within 25 km. Step out ring by ring:

12 projects within 1 km — showing the nearest 6.

SakhroliResidential / Group Housing

PITAMBARI INDRADHANU VILLAGE

PITAMBARI PRODUCTS PVT LTD

Dec 2020registered
Jun 2027target completion
Scale113 flatsAuthorityMahaRERA
JalgaonResidential / Group Housing

Whistling Meadows

Jeetesh Shankar Parihar

Mar 2021registered
Jun 2026target completion
AuthorityMahaRERA
Dapoli CampOthers

AARTI APARTMENT

Aniruddha Subhashchandra Butala

Dec 2022registered
Dec 2026target completion
Scale15 flatsAuthorityMahaRERA
Dapoli CampResidential / Group Housing

Milestone

Chandrashekhar Sadashiv Lawate

Feb 2025registered
May 2027target completion
Scale55 flatsAuthorityMahaRERA
Dapoli CampOthers

DATTA ARCADE

NIKET RAMESH MEHTA

Nov 2024registered
May 2027target completion
Scale32 flatsAuthorityMahaRERA
Dapoli CampResidential / Group Housing

SHREEJI SPARSH

SHREE KRISHNA BUILDCON

Nov 2024registered
Aug 2031target completion
Scale61 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.