HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
9
Buildings
6
Parking
103 spaces
Land area
2,961 sq m
Sanctioned built-up
8,976 sq m
Recreational open space
296 sq m

Timeline

RERA registeredNov 2024
Proposed completionDec 2027
TodayJul 2026
Construction progress
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
Open Parking0%
Flat fit-out20%
Internal finishes50%
Stairs & lifts50%
Superstructure80%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Stilt floor100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Gopal Balaprasad Ajmera

IndividualPromoter type
Aurangabad, MAHARASHTRABased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Aurangabad (M Corp.)
Taluka
Aurangabad
District
Aurangabad
Pincode
431005
Survey no.
Gut no. 22/Part, Mauje Shahnoorwadi
North boundary
Satara Shiv Gut no 20
East boundary
Satara Shiv
South boundary
Beed By Pass road
West boundary
Shahnoorwadi Gut no 23
What’s nearby
SchoolsNearest school 1.4km away
HealthcareHospital 55m away · 1 clinic within 1km
LifestylePark 1.4km away · Gym or sports centre 1.2km away
ShoppingSupermarket 1.6km away
Getting around
Expressway 181 m · Beed Bypass HighwayPrimary road 2.7 km · Kranti ChowkRailway line 379 mRailway station 2.7km away (Chhatrapati Sambhajinagar)Bus stop within 1km
Water & environment
River 1.8 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Aurangabad Municipal Corporation

Municipal Corporation
Building Permit
Survey no. Gut no. 22/Part, Mauje Shahnoorwadi
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Aurangabad Municipal Corporation

Municipal corporation

Has approved 54 RERA projects0.3% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
53
On record
324 flats · 0 plots
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.