HORIZONMarkets
01

Complete project overview

K-RERA · Registration filing
Units
15 units
Mix
10 × 2BHK · 5 × 3BHK
Booked
11 of 15 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
752 sq m
Floor area
2,097 sq m
Description
ADDRESS ASHRAMAM

Timeline

Project startedJan 2023
RERA registeredJan 2023
Proposed completionMar 2026
TodayJul 2026
Construction progress

50% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation100%
Basement(s) and Plinth100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

4 of 15 available
TypeArea sq mAvailable
2BHK770 of 4
2BHK732 of 6
3BHK932 of 4
3BHK1360 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

ADDRESS BUILDERS AND DEVELOPERS LLP

Limited Liability PartnershipPromoter type
Kollam, KeralaBased in
No — the promoter declared this is a first projectDeclared prior experience
1Projects
1Cities
2023–2026Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
Asramam
Village
KOLLAM EAST
Taluk
Kollam
District
Kollam
Pincode
691001
Survey no.
52
Patta no.
30680
What’s nearby
SchoolsNearest school 1.4km away · College or university 1.2km away · Library 234m away
HealthcareHospital 844m away · Clinic within 2km
Lifestyle2 parks within 500m · Gym or sports centre 1.6km away · 10+ restaurants and cafes within 1km
ShoppingSupermarket 1.3km away · Mall 1.0km away · Bank 757m away
Getting around
Expressway 2.9 km · Neeravil BridgePrimary road 959 m · Salem - Kochi - Kanyakumari RoadRailway line 1.1 kmRailway station 1.2km away (Kollam Junction)Bus stop within 500m
Water & environment
Water body 546 m · Adventure Park Pond
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

K-RERA · Approved building plan

Kollam Municipal Corporation

Municipal Corporation
approved 10 Oct 2022 · 3 yrs ago
Building Permit no. TP3/BA/5/2022-23Survey no. 52

The promised possession date (26 Mar 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan TP3/BA/5/2022-23 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Kollam Municipal Corporation

Municipal corporation / municipality

Has approved 11 RERA projects0.7% of Kerala.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
9
On record
579 flats · 0 plots
Since
2021

More apartment-heavy than Kerala overall — 100% apartments here vs 81% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.