HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
32
Buildings
2
Parking
562 spaces
Land area
8,414 sq m
Sanctioned built-up
12,918 sq m
Recreational open space
4,313 sq m

Timeline

RERA registeredAug 2017
Proposed completionMar 2031
TodayJul 2026
Construction progress
Basement (if any)0%
Aggregate area of …0%
GYM0%
CCTV0%
Internal finishes50%
Flat fit-out50%
Superstructure52%
Fire protection an…55%
Electrical meter r…55%
Stairs & lifts60%
External finishes60%
OC-readiness60%
Water Supply70%
Sewerage (Chamber,…70%
Water conservation…70%
Excavation100%
Podiums100%
Plinth100%
Stilt floor100%
Storm Water Drains100%
Landscaping & Tree…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Jayant Shashikant Parikh

IndividualPromoter type
Thane, MAHARASHTRABased in
1Projects
1City
2017–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Airoli
Taluka
Thane
District
Thane
Pincode
400708
Survey no.
Plot No.1,Sector-19 & Plot No.11B,Sector-3
North boundary
15 meter wide road
East boundary
plot 11 a sector 3
South boundary
plot no 2
West boundary
plot 1 a
What’s nearby
Schools1 school within 1km
HealthcareHospital 188m away · 1 clinic within 1km
Lifestyle1 park within 500m · Gym or sports centre 1.4km away · 6 restaurants and cafes within 1km
ShoppingSupermarket 1.4km away · Mall 1.2km away · Convenience store within 1km
Getting around
Expressway 2.8 km · Mumbra-Kausa BypassPrimary road 647 m · Thane Belapur RoadRailway line 691 m · Trans-Harbour LineRailway station 3.4km away (Thane)8 bus stops within 500m
Water & environment
Water body 714 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Navi Mumbai Municipal Corporation (Nmmc)

Municipal Corporation
Building Permit
Survey no. Plot No.1,Sector-19 & Plot No.11B,Sector-3
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation

A city municipal corporation that sanctions projects within its own limits. It has approved 12,653 RERA projects across 34 districts about 1 in 2 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
Litigation1 case on record, earliest 2009
Compliance1 non-compliance notice on record
Appeals4 appeals before the tribunal
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

5 complaints on MahaRERA’s register for this project 5 disposed.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.